Slippery Rock College is planning a basketball tournament. The following infor-mation has been collected on each activity in the project:
Days Immediate Predecessor Description
A 3 - Select teams
B 5 A Mail out invitations
C 10 - Arrange accommodations
D 3 B,C Plan promotion
E 5 B,C Print tickets F 10 E Sell tickets
G 8 C Complete arrangements
H 3 G Develop schedules
I 2 D,H Practice
J 3 F,I Conduct tournament
a. Draw a network diagram of this project, and label the activities and events.
b. Calculate the total slack and scheduling times for all activities. What is the criti-cal path?
c. When should team selection begin if the tournament is scheduled to start on the morning of December 27? (Include Saturday and Sunday as working days.)