A new engineering team is put together for the development of a new product. This new product will be built through an assembly line. The production manager designs the assembly line. He has been advised that the assembly line must be ready in four weeks (20 working days) for a test run. The manager decided to use CPM (critical path method) and has broken down the projects into the following activities, determined their precedence relationships, and estimated normal times:
Activity
|
Immediate Predecessors
|
Normal Time (days)
|
Crash Time (days)
|
Crashing Cost ($/ day)
|
a. organize layout team
|
none
|
5
|
5
|
-
|
b. organize modification team
|
none
|
3
|
3
|
-
|
c. design personnel jobs
|
a, b
|
2
|
1
|
500
|
d. set machinery in place
|
none
|
3
|
1
|
2500
|
e. connect utilities
|
d
|
3
|
4
|
1000
|
f. modify conveyor system
|
c, e
|
4
|
3
|
1200
|
g. train personnel
|
c
|
3
|
3
|
-
|
h. finishing touches
|
f, g
|
5
|
3
|
800
|
i. run test lot
|
h
|
2
|
2
|
-
|
Based on the information provided above, answer the following questions.
1. What is the project earliest completion time in days? Round your answer to the nearest integer. Your answer is .
2. What is the EST of activity g? Round your answer to the nearest integer. Your answer is .
3. What is the LST of activity c? Round your answer to the nearest integer. Your answer is .
4. What is the LST of activity g? Round your answer to the nearest integer. Your answer is .
5. What is the slack time of activity g? Round your answer to the nearest integer. Your answer is .
6. How many critical tasks are on the critical path (excluding S and T)? Round your answer to the nearest integer. Your answer is .
7. The manager would like to expedite the project by 1 day. According to the crashing data provided in the table, which task should be expedited? Input the task label here. For example, if your answer is a - organizing layout team, input a. Your answer is .
What is shareholders equity
: Construct a balance sheet for Sophie’s Sofas given the following data. What is shareholders’ equity?
|
Maker of winglow is purchasing new stamping machine
: The maker of Winglow is purchasing a new stamping machine. Two options are being considered, Rooney and Blair. The sales forecast for Winglow is 8,750 units for next year. If variable costs are now $20 per unit, which machine should be purchased? Bl..
|
Determine whether f is a mnetion from z to r it if
: Determine whether f is a Mnetion from Z to R It if. Determine whether each of these function from Z to Z is 1-1 or is an injection. Justify your answer.
|
What is the inventory turnover
: Net sales on account during year $517, 500 Cost of merchandise sold during year 450,000 Accounts receivable. -Based on the following data for the current year, what is the inventory turnover?
|
Development of a new product
: A new engineering team is put together for the development of a new product. This new product will be built through an assembly line. The production manager designs the assembly line. He has been advised that the assembly line must be ready in fou..
|
How a system may use the data in this warehouse to work
: The movement data may be sparse. Discuss how you would develop a method that constructs a reliable data warehouse despite the sparsity of data.
|
Describe how the defects detected during the acceptance
: Develop a workflow model that can be used to inspect and detect defects during the acceptance of this mobile product through the use of graphical tools in Microsoft Word or Visio, or an open source alternative such as Dia. Note: The graphically de..
|
What special challenges are agencies and specifically
: What special challenges are agencies and specifically Chief's of police facing in this current environment? What steps would you take to address those current challenges? Please provide examples.
|
What is the value of the call option
: Suppose the current price of MDD stock is $90. -What is the value of the call option if the exercise price is $75 per share?
|