Assume that you have been selected to serve as the project manager for a management consulting project for a client based in the United States. You have developed the WBS and listed the activities for the assignment, which involve large-scale market research in a new market. You are responsible for project costs and are keen on developing realistic cost estimates and project budget. You have estimated the following effort:
WBS
Tasks
Duration
Resource Type
Effort in Days
1.1
Final proposal and contract documentation
4 Days
Junior Consultant
4
Legal Consultant
1
Vice President
1.2
Assignment kickoff workshop
2 Days
2
Senior Consultant
2.1
Designing market research
5 Days
Product Expert
5
2.2
Pilot run of market research
10 Days
3
Intern
10
2.3
Final market research design and signoff
2.4
Market research 1
32 Days
20
2 Interns*
28
2.5
Market research 2
2.6
Data collation and analysis
0.5
3.1
Final report preparation
3 Days
3.2
Presentation to client
1 Day
*Please note the use of 2 resources in this case. The rates per day for the resources are as follows:
Resource
Rate Per Day
$750
$250
$1,500
$3,500
The tasks above are listed in sequential order. The exceptions are market research 1 and 2, which can start simultaneously.
Part 1: Develop the budget for this project by allocating cost over actual work time and the calendar time line. Draw a graph for the time line of the project and the money spent on the project. Assume that the payments to all resources are made on a daily basis.
Part 2: For the consulting assignment, assume that the total project budget is spent equally on a daily basis and the work done each day contributes equally toward the project completion. You are now at the end of Day 25 of the project, the company has already spent $48,000, and the project has delivered 5% more than planned at the end of Day 25.
Describe application architecture also process design. Include a high-level description of security controls which you recommend for design of this HR system. Apply tools of systems analysis to describe information systems architecture in terms of..
customers per hour and an average service time of 18 minutes per customer. What are the minimum number of servers required to avoid an overloaded system?
Which would be the required qualifications to consider a employee for a top management position?
Are long-term objectives helping the enterprise make appropriate strategic choice decisions? How do distinctions between value disciplines
Although there was ample demand for business courses last semester, conflicting schedules allowed only 1,450 new students to take business courses. Illustrate what are the utilization and efficiency of this system.
The holding cost is 10 percent of the purchase cost. How many units should R. C. order to minimize his total annual inventory cost?
Describe a specific well functioning team you performed on; the role you played, the goal of the team, the positive attributes of the project and why you believed the team was successful - related back to the specifics of team development.
Develop an example of planning in personal decision making. Perhaps you will discuss the steps as they relate to planning a family vacation, finding a new job, buying a new house
Identify two key components of service system quality. Explain why these components are particularly important to service system quality
Select one tool, other than MS Project, that you could use in order to manage project costs and scheduling. Next, speculate on the overall different project management strategy that you would apply based on the tool that you have selected
A town's department of public works is concerned about adverse public reaction to a sewer project that is currently in progress. Because of this, the Commissioner of Public Works has authorized a weekly survey to be conducted of town residents
The earnings, dividends, and common stock price of Carpetto Technologies Inc. are expected to grow at 8% per year in the future.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd