Assume that you have been selected to serve as the project manager for a management consulting project for a client based in the United States. You have developed the WBS and listed the activities for the assignment, which involve large-scale market research in a new market. You are responsible for project costs and are keen on developing realistic cost estimates and project budget. You have estimated the following effort:

WBS

Tasks

Duration

Resource Type

Effort in Days

1.1

Final proposal and contract documentation

4 Days

Junior Consultant

4




Legal Consultant

1




Vice President

1

1.2

Assignment kickoff workshop

2 Days

Junior Consultant

2




Senior Consultant

1




Vice President

1

2.1

Designing market research

5 Days

Product Expert

1




Junior Consultant

5




Senior Consultant

2

2.2

Pilot run of market research

10 Days

Junior Consultant

3




Intern

10




Senior Consultant

2

2.3

Final market research design and signoff

2 Days

Junior Consultant

2




Senior Consultant

1




Vice President

1

2.4

Market research 1

32 Days

Junior Consultant

20




Senior Consultant

2




2 Interns*

28

2.5

Market research 2

32 Days

Junior Consultant

20




Senior Consultant

2




2 Interns*

28

2.6

Data collation and analysis

5 Days

Junior Consultant

5




Senior Consultant

3




2 Interns*

5




Vice President

0.5

3.1

Final report preparation

3 Days

Senior Consultant

3




Junior Consultant

3




Vice President

0.5

3.2

Presentation to client

1 Day

Senior Consultant

1




Junior Consultant

1




Vice President

0.5

*Please note the use of 2 resources in this case.
The rates per day for the resources are as follows:

Resource

Rate Per Day

Junior Consultant

$750

Intern

$250

Legal Consultant

$1,500

Product Expert

$3,500

Senior Consultant

$1,500

Vice President

$3,500


The tasks above are listed in sequential order. The exceptions are market research 1 and 2, which can start simultaneously.

Part 1:
Develop the budget for this project by allocating cost over actual work time and the calendar time line. Draw a graph for the time line of the project and the money spent on the project. Assume that the payments to all resources are made on a daily basis.

Part 2:
For the consulting assignment, assume that the total project budget is spent equally on a daily basis and the work done each day contributes equally toward the project completion. You are now at the end of Day 25 of the project, the company has already spent $48,000, and the project has delivered 5% more than planned at the end of Day 25.

  • What is your assessment of the schedule performance index (SPI) and cost performance index (CPI) of the project? What actions or corrective actions would you want to take, keeping in mind the project performance so far?
  • How much more money must be spent to complete the project, and what would be the total cost of the project when it is completed, as per the details given?

Reference no: EM13232657

Questions Cloud

What is the cause of disputes and the contractual means : What is the cause of disputes and the contractual means used for resolving them?
Examine arbitration as a quasi judicial process : Examine arbitration as a quasi judicial process in which parties agree to submit unresolved disputes to a neutral third party for binding settlement. Explain the labor- contractual negotiations in detail.
How do you write a program that compares your checking : How do you write a program named Balance.java that compares your checking account balance with your savings account balance (two doubles)
Explain what is the capacity of the buffer : a buffer is created by mixing 26 mL of 3.3M sodium formate and 16 mL of 3 M formic acid. What is the capacity of the buffer if 0.2 M NaOH is added?
Develop the budget for project by allocating cost over : Develop the budget for project by allocating cost over actual work time and the calendar time line. Draw a graph for the time line of the project and the money spent on the project.
Define the result of doubling the initial concentration of x : The reaction x = Y is first -order overall and first-order with respect to the reactant x. The result of doubling the initial concentration of X will be to
Explain how many moles of strong base : consider a .7 L of a buffer composed of 0.4 M HClO and 0.5 NaClO? How many moles of strong base could this buffer withstand?
Are business mergers good or bad for the economy : (a) What is market concentration and how can you know whether a market is concentrated or not (b) What are the causes of market concentration (c) Are business mergers good or bad for the economy Explain why
How fiscal policy would affect aggregate demand : Can you explain how FISCAL POLICY (making changes to government spending and taxes) would affect Aggregate Demand (AD) How do these two mechanisms of expansionary policy differ

Reviews

Write a Review

Operation Management Questions & Answers

  Describe information systems architecture in terms of data

Describe application architecture also process design. Include a high-level description of security controls which you recommend for design of this HR system. Apply tools of systems analysis to describe information systems architecture in terms of..

  What are the minimum number of servers required

customers per hour and an average service time of 18 minutes per customer. What are the minimum number of servers required to avoid an overloaded system?

  Which would be required qualifications to consider employee

Which would be the required qualifications to consider a employee for a top management position?

  Are long-term objectives helping the enterprise make

Are long-term objectives helping the enterprise make appropriate strategic choice decisions? How do distinctions between value disciplines

  Illustrate what are the utilization and efficiency system

Although there was ample demand for business courses last semester, conflicting schedules allowed only 1,450 new students to take business courses. Illustrate what are the utilization and efficiency of this system.

  How many units should r c

The holding cost is 10 percent of the purchase cost. How many units should R. C. order to minimize his total annual inventory cost?

  Describe a specific well functioning team you performed on

Describe a specific well functioning team you performed on; the role you played, the goal of the team, the positive attributes of the project and why you believed the team was successful - related back to the specifics of team development.

  Develop an example of planning in personal decision making

Develop an example of planning in personal decision making. Perhaps you will discuss the steps as they relate to planning a family vacation, finding a new job, buying a new house

  Identify two key components of service system quality

Identify two key components of service system quality. Explain why these components are particularly important to service system quality

  Project management strategy

Select one tool, other than MS Project, that you could use in order to manage project costs and scheduling. Next, speculate on the overall different project management strategy that you would apply based on the tool that you have selected

  A town''s department of public works is concerned

A town's department of public works is concerned about adverse public reaction to a sewer project that is currently in progress. Because of this, the Commissioner of Public Works has authorized a weekly survey to be conducted of town residents

  Compute the firm cost of common equity

The earnings, dividends, and common stock price of Carpetto Technologies Inc. are expected to grow at 8% per year in the future.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd