Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activi- ties would have to be undertaken before construction can begin:

Activity

Description

Immediate Predecessor

Time (weeks)

A

Survey building site

-

6

B

Develop initial design

-

8

C

Obtain board approval

A, B

12

D

Select architect

C

4

E

Establish budget

C

6

F

Finalize design

D, E

15

G

Obtain financing

E

12

H

Hire contractor

F, G

8

a. Draw a project network.

b. Identify the critical path.

c. Develop the activity schedule for the project.

d. Does it appear reasonable that construction of the athletic complex could begin one year after the decision to begin the project with the site survey and initial design plans? What is the expected completion time for the project?

Reference no: EM13918836

Questions Cloud

Sale of government-owned economic resources : Question 1: The sale of government-owned economic resources to private operators is called _______.
What market application envision of greptile grip technology : What new market applications (outside of sports and leisure) do you envision for the Greptile grip technology? Justify why you think these new market applications are warranted.
Determine the value of the bond : National Steel 15-year, $1000 par value bonds pay 5.5 percent interest annually. The market price of the bonds is &1,085, and your required rate of return is 7 percent. a. Compute the bonds expected rate of return. b. Determine the value of the bond ..
Planning the audit of a client financial statements : (Assertions) In planning the audit of a client's financial statements, an auditor identified the following issues that need audit attention.
Develop the activity schedule for the project : Develop the activity schedule for the project. Does it appear reasonable that construction of the athletic complex could begin one year after the decision to begin the project with the site survey and initial design plans?
Component in a healthy visual arts ecology : ‘Sound business models are a necessary component in a healthy visual arts ecology and essential for most publicly funded organisations' (Royce, 2011, p. 3)
What must be the opportunity cost of capital : A stock sells for $30. The next dividend will be $3 per share. If the return on equity ROE is a constant 15% and the company reinvests 40% of earnings in the firm, what must be the opportunity cost of capital?
Biggest nursing service lines : Sacred Heart Hospital (SHH) faces skyrocketing nursing costs, all of which relate to its two biggest nursing service lines - the Emergency Room (ER) and the Operating Room (OR). SHH's current cost system assigns total nursing costs to the ER and OR b..
Long butterfly spread from options with strike prices : A trader creates a long butterfly spread from options with strike prices of $60, $65, and $70 per share by trading a total of 60 option contracts (15 contracts at $60, 30 contracts at $65 and 15 contracts at $70). Each contract is written on 100 shar..

Reviews

Write a Review

Operation Management Questions & Answers

  What is data and why is it important to a business

What is data and why is it important to a business. What is the relationship between data, information, business intelligence, and knowledge

  Heuristics for prioritizing resource allocation

What are any four heuristics for prioritizing resource allocation to activities. Why would a project manager choose one above another

  Structures of the hotel business

From the e-Activity, determine which position would be the most difficult to execute correctly. Provide specific examples of the challenges that position would present, as well as how you would address those challenges.

  Discuss the basic relationships in an mrp system

Discuss the basic relationships in an mrp system. Use the text and any other resources for this project. I am intentionally giving a lot of latitude here so you can either find an article that suits you or take a more basic approach to increase y..

  Diversification would be a particularly good strategy

List and discuss some guidelines for when related diversification would be a particularly good strategy to pursue.

  At what volume of output would the two alternatives yield

At what volume of output would the two alternatives yield the same profit? c. If demand is 13000 unites, which options yeilds a higher profit and how much?

  What are the strategies you might use

If you work for a food and beverage MNC seeking a partnership opportunity, what are the strategies you might use? Provide reasons to support your choices.

  How much of impact does maturity level of the industry

How much of an impact does the "maturity" level of the industry or company have on strategy? How can you be innovative in a mature industry? How can you be conservative in an introductory/rapid growth situation?

  Question 1melissa bakery is preparing for the coming

question 1melissa bakery is preparing for the coming thanksgiving festival. the bakery plans to bake and sell its

  Eoq increase or decrease if estimates of setup

Does the EOQ increase or decrease if estimates of setup (order) costs include fixed, semi-variable, and pure variable costs while inventory-holding costs include only pure variable costs? Vice versa? What are the implications? Explain.

  How can the lessons of operations management

How can the lessons of operations management be used to increase the efficiency and effectiveness of service delivery to the customer?

  Explain the additional costs associated with shipping

When a product is shipped from the U.S. to another country, there are some extra costs associated with the way the product should be packaged and prepared. Choose a product from a company that is scheduled to be shipped internationally. Explain the a..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd