Develop network for planning and construction of hospital

Assignment Help Operation Management
Reference no: EM131352426

Project Management at Arnold Palmer Hospital

The equivalent of a new kindergarten class is born every day at Orlando's Arnold Palmer Hospital. With more than 13,000 births in the mid-2000s in a hospital that was designed 15 years earlier for a capacity of 6,500 births a year, the newborn intensive care unit was stretched to the limit. Moreover, with continuing strong population growth in central Florida, the hospital was often full. It was clear that new facilities were needed. After much analysis, forecasting, and discussion, the management team decided to build a new 273-bed building across the street from the existing hospital. But the facility had to be built in accordance with the hospital's Guiding Principles and its uniqueness as a health center dedicated to the specialized needs of women and infants. Those Guiding Principles are: Family-centered focus, a healing environment where privacy and dignity are respected, sanctuary of caring that includes warm, serene surroundings with natural lighting, sincere and dedicated staff providing the highest quality care, and patient-centered flow and function . The vice president of business development, Karl Hodges, wanted a hospital that was designed from the inside out by the people who understood the Guiding Principles, who knew most about the current system, and who were going to use the new system, namely, the doctors and nurses. Hodges and his staff spent 13 months discussing expansion needs with this group, as well as with patients and the community, before developing a proposal for the new facility. An administrative team created 35 user groups, which held over 1,000 planning meetings (lasting from 45 minutes to a whole day). They even created a "Supreme Court" to deal with conflicting views on the multifaceted issues facing the new hospital.

Table - Expansion Planning and Arnold Palmer Hospital Construction Activities and Times

ACTIVITY

SCHEDULED TIME

PRECEDENCE ACTIVITY(IES)

1. Proposal and review

1 month

-

2. Establish master schedule

2 weeks

1

3. Architect selection process

5 weeks

1

4. Survey whole campus and its needs

1 month

1

5. Conceptual architect's plans

6 weeks

3

6. Cost estimating

2 months

2, 4, 5

7. Deliver plans to board for consideration/decision

1 month

6

8. Surveys/regulatory review

6 weeks

6

9. Construction manager selection

9 weeks

6

10. State review of need for more hospital beds ("Certificate of Need")

3.5 months

7, 8

11. Design drawings

4 months

10

12. Construction documents

5 months

9,11

13. Site preparation/demolish existing building

9 weeks

11

14. Construction start/building pad

2 months

12, 13

15. Relocate utilities

6 weeks

12

16. Deep foundations

2 months

14

17. Building structure in place

9 months

16

18. Exterior skin/roofing

4 months

17

19. Interior buildout

12 months

17

20. Building inspections

5 weeks

15, 19

21. Occupancy

1 month

20

Funding and regulatory issues added substantial complexity to this major expansion, and Hodges was very concerned that the project stay on time and within budget. Tom Hyatt, director of facility development, was given the task of onsite manager of the $100 million project, in addition to overseeing ongoing renovations, expansions, and other projects. The activities in the multiyear project for the new building at Arnold Palmer are shown in Table.'

Discussion Questions

1. Develop the network for planning and construction of the new hospital at Arnold Palmer.

2. What is the critical path, and how long is the project expected to take?

3. Why is the construction of this 11-story building any more complex than construction of an equivalent office building?

4. What percent of the whole project duration was spent in planning that occurred prior to the proposal and reviews? Prior to the actual building construction? Why?

Reference no: EM131352426

Questions Cloud

What will be approximate capital gain of bond : A bond has a par value of $1,000, a time to maturity of 15 years, and a coupon rate of 9.00% with interest paid annually. if the current market price is $900, What will be the approximate capital gain of this bond over the next year if its yield to m..
Difference between and haploid number and ploidy number : What is the difference between and haploid number and a ploidy number, and how do you determine them?
Compose a documentation entry to describe community health : Community health RN is caring for a family with a child who has significant developmental delays. The child is 9-years-old and exhibits the development of a 6-month old infant. She can move her extremities spontaneously, hold her head up and cry ..
What is perimeter of rectangle to nearest tenth of a unit : The coordinates of the vertices of a rectangle are (5,2) , (-1,4) , (4,-1) and (-2,1). What is the perimeter of the rectangle to the nearest tenth of a unit?
Develop network for planning and construction of hospital : Develop the network for planning and construction of the new hospital at Arnold Palmer. What is the critical path, and how long is the project expected to take
Generations of lizards-short legs or long legs : Review the data that was collected concerning the distance traveled by individuals categorized by short or long legs. Which trait may have the greatest chance of being passed down to future generations of lizards-short legs or long legs?
Compute value of this stock with required return : A firm is expected to pay a dividend of $2.25 next year and $2.55 the following year. Financial analysts believe the stock will be at their price target of $100 in two years. Compute the value of this stock with a required return of 11.2 percent.
Discuss an everyday application of the scientific method : Discuss An Everyday Application of the Scientific Method Science is a systematic method of learning about the universe that relies on logic and revolves around the notion of cause and effect. There is a great deal of variation in the specific tech..
Describe how the agencies you chose are alike : Choose two homeland security agencies at the federal, state, or local level to compare and contrast. Describe how the agencies you chose are alike, how they are different, and areas for improvement.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd