Develop an estimate of variable electricity costs

Assignment Help Managerial Accounting
Reference no: EM132798614

Question - Machine hours and electricity costs for Wells Industries for the year 2011 are as follows:

Month

Machine Hours

Electricity Costs

January

2,000

9,200

February

2,320

10,500

March

1,520

6,750

April

2,480

11,500

May

3,040

14,125

June

2,640

11,000

July

3,280

12,375

August

2,800

11,375

September

1,600

7,750

October

2,960

13,000

November

3,760

15,500

December

3,360

13,875

Required -

A. Using the least square method, develop an estimate of variable electricity costs per machine hour.

B. Using the least square method, develop an estimate of fixed electricity costs per month.

Reference no: EM132798614

Questions Cloud

What is backward vertical integration : What is horizontal integration and identify two reasons why horizontal integration fails?
Find optimal number of pencils for the bookstore to purchase : Number 2 pencils at the campus bookstore are sold at a fairly steady rate of 60 per week. The pencils cost the bookstore 2 cents each and sell for 15 cents each
Types of roles and responsibilities of health informaticians : Consider the types of roles and responsibilities of health informaticians.
Difference between qualitative tools vs quantitative tool : What is the difference between qualitative tools versus quantitative tools? Select and summarize the purpose of ONE Qualitative Tool
Develop an estimate of variable electricity costs : Machine hours and electricity costs for Wells Industries for the year 2011 are as follows: develop an estimate of variable electricity costs per machine hour
Identify the list of risk associated with the bioops : Provide minimum of two tools or techniques we can use to identify the list of risk associated with the BioOps to apply to scope in consultation with other relev
Describe a typical fast-food restaurant : Why does the ratio of labor cost to food cost differ between fast food and fine dining restaurants? Describe a typical fast-food restaurant's labor
Organizations achieve a competitive advantage : 1. Identify how changes in the external environment may affect the Operations Management (OM) strategy for a company. For example, what impact are the following
What is the bottleneck time of work cell : The three-station work cell illustrated in Figure S7.7 has a product that must go through one of the two machines at station 1 (they are parallel) before procee

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd