Develop a cpm network for moore house contractors

Assignment Help Operation Management
Reference no: EM13922166

Moore Housing Contractors

Moore Housing Contractors is negotiating a deal with Countryside Realtors to build six houses in a new development. Countryside wants Moore Contractors to start in late winter or early spring when the weather begins to moderate and build through the summer into the fall. The summer months are a busy time for the realty company, and it believes it can sell the houses almost as soon as they are ready-sometimes before. The houses all have similar floor plans and are of approximately equal size; only the exteriors are noticeably different. The completion time is so critical for Countryside Realtors that it is insisting a project management network accompany the contractor''s bid for the job with an estimate of the completion time for a house. The realtor also needs to be able to plan its offerings and marketing for the summer. The realtor wants each house to be completed within 45 days after it is started. If a house is not completed within this time frame, the realtor wants to be able to charge the contractor a penalty. Mary and Sandy Moore, the president and vice president of Moore Housing Contractors, are concerned about the prospect of a penalty. They want to be confident they can meet the deadline for a house before entering into any agreement with a penalty involved. (If there is a reasonable likelihood they cannot finish a house within 45 days, they want to increase their bid to cover potential penalty charges.)

The Moores are experienced home builders, so it was not difficult for them to list the activities involved in building a house or to estimate activity times. However, they made their estimates conservatively and tended to increase their pessimistic estimates to compensate for the possibility of bad weather and variations in their workforce. Following is a list of the activities for building a house and the activity time estimates:

Time (days)

Activity Description Predecessor a m b
a Excavation, pour footers - 3 4 6
b Lay foundation a 2 3 5
c Frame and roof b 2 4 5
d Lay drain tiles b 1 2 4
e Sewer (floor) drains b 1 2 3
f Install insulation c 2 4 5
g Pour basement floor e 2 3 5
h Rough plumbing, pipes e 2 4 7
i Install windows f 1 3 4
j Rough electrical wiring f 1 2 4
k Install furnace, air conditioner c, g 3 5 8
l Exterior brickwork i 5 6 10
m Install plasterboard, mud, plaster j, h, k 6 8 12
n Roof shingles, flashing l 2 3 6
o Attach gutter, downspouts n 1 2 5
p Grading d, o 2 3 7
q Lay subflooring m 3 4 6
r Lay driveway, walks, landscape p 4 6 10
s Finish carpentry q 3 5 12
t Kitchen cabinetry, sink, and appliances q 2 4 8
u Bathroom cabinetry, fixtures q 2 3 6
v Painting (interior and exterior) t, u 4 6 10
w Finish wood floors, lay carpet v, s 2 5 8
x Final electrical, light fixtures v 1 3 4

1. Develop a CPM/PERT network for Moore House Contractors and determine the probability that the contractors can complete a house within 45 days. Does it appear that the Moores might need to increase their bid to compensate for potential penalties?

2. Indicate which project activities Moore Contractors should be particularly diligent to keep on schedule by making sure workers and materials are always available. Also indicate which activities the company might shift workers from as the need arises.

Verified Expert

Reference no: EM13922166

Questions Cloud

What are the potential causes of a projects failure : The Department of Defense (DOD) has a record of both successful projects and failed projects. Discuss when a project is, at any organization, considered successful and when it is considered a failure. What are the potential causes of a project's f..
Balance sheet-total liabilities and assets-equity : Jill's Wigs Inc. had the following balance sheet last year: Cash $800 Accounts payable $350 Accounts receivable $450 Accrued wages $150 Inventory $950 Notes payable $2,000 Net fixed assets $34,000 Mortgage $26,500 Common stock $3,200 Retained earning..
Problem regarding the computer networks assignment : Both the CSMA/CD with Token bus medium access control methods can be used in real time systems. Which one is better suited for real time applications? Explain.
Who need to be involve in decision to purchase an erp system : Who in the organization needs to be involved in designing and implementing MRP II? Who needs to be involved in the decision to purchase an ERP system? Who needs to be trained to use ERP?
Develop a cpm network for moore house contractors : Develop a CPM/PERT network for Moore House Contractors and determine the probability that the contractors can complete a house within 45 days. Does it appear that the Moores might need to increase their bid to compensate for potential penalties?
Explained one page essay on the history of computers : Explained one page essay on the history of computers. Please focus on computer generations only
What is equity value and debt value on a market value basis : Dinklage Corp. has 4 million shares of common stock outstanding. The current share price is $83, and the book value per share is $8. The company also has two bind issues outstanding. The first bond issue has a face value of $90 million, a coupon of 6..
Determine the fixed rate on the swap : Given interest rate options with notional principals of $10 million on an underlying 120-day LIBOR. The options have exercise rates of 6% and will expire in 30 days. What is the payoff on the call option if the LIBOR in 30 days is 7%, in 60 days is..
What emotions were the images intended to elicit : Considering all the primary visual sources, as well as the propaganda poems and speeches, how are Germans portrayed? What emotions were the images intended to elicit

Reviews

Write a Review

Operation Management Questions & Answers

  Opportunities to capitalize on proven market successes

Founders using a pioneering new entry strategy look for opportunities to capitalize on proven market successes. Do you agree? Why?

  Describe key characteristics to classify wheeled coach

What are the key characteristics that would classify Wheeled Coach as a repetitive focus process strategy?

  What should the use of sales data instead of demand imply

Predict orders for the following day for each of the products using an appropriate naïve method.

  Future trends

Look into the future. Consider trends in society, technology, economics, environmentalism, and politics that can influence PROCTOR & GAMBLE (P&G). Be sure to look beyond the company's current market, product, and geographic boundaries. Identify two o..

  Compare and contrast the types of production

Compare and contrast the types of production processing-job shop, batch, repetitive, or continuous-and determine which the primary mode of operation is and why.

  Swot analysis is focused on strengths and weaknesses

The SWOT analysis is focused on the strengths, weaknesses, opportunities, and threats that exist for a firm. Think about being an employee for a firm. Which one is most important to you? Now think of yourself as the CEO or owner of the firm. Does thi..

  Dells capacity to produce computers

What impact would change have on Dell's capacity to produce computers and what operations strategy could Dell be attempting with a move

  Attitudes toward a restructuring of the basic cable service

Klien Research has been hired to survey cable television customers to determine their attitudes toward a restructuring of the basic cable service and rate schedule. The cable company wants to classify participants according to whether or not there ar..

  Describe the remedies available to gadgets galore

WidgetsRUS immediately sends an objection to the confirmation to Gadgets Galore. Describe the remedies available to Gadgets Galore under the Uniform Commercial Code?

  Complete a risk assessment of all risks associated with this

Describe the measureable value. This should include a cost-benefit analysis, such as payback period or ROI that relies on tangible measures of organizational value through cost savings, revenue enhancements, or improvements in the speed

  Find economies of scope provide examples of specific actions

Find economies of scope. Provide examples of specific actions Harley-Davidson's managers could take to reduce expenses or share activities through horizontal relationships across brands.

  Describe four qualitative forecasting techniques

Review the following learning objective from the text: Describe four qualitative forecasting techniques. Then, explain why you agree or disagree with the following statement:Knowledge about what customers are likely to do is much more valuable than i..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd