Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
Q1) Miracle Marketing has received construct from a large pharmaceutical firm to design nationwide advertising campaign for their recently approved cancer drug. Drug is easily taken, compared with present intravenous drugs, and can be administered from home. Miracle Marketing has alloted to task a project manager who, in turns has delegated minor subprojects to subordinate managers.
Project was estimated by using ADM/PERT analysis. Due to extensive length of project many activities were combined; Following is the result.
Activity
Time(month)
AB
3
BC
6
BD
2
BF
5
BE
4
CD
9
DG
20
FG
EH
11
EI
19
GJ
1
HK
IL
LM
12
KN
7
JO
MN
15
NP
13
OP
10
Determine the critical path and expected completion date.
MATH1550H: Assignment: Question: A word is selected at random from the following poem of Persian poet and mathematician Omar Khayyam (1048-1131), translated by English poet Edward Fitzgerald (1808-1883). Find the expected value of the length of th..
MATH1550H: Assignment: Question: what is the least number of applicants that should be interviewed so as to have at least 50% chance of finding one such secretary?
MATH1550H: Assignment: Question: Experience shows that X, the number of customers entering a post office during any period of time t, is a random variable the probability mass function of which is of the form
MATH1550H: Assignment:Questions: (Genetics) What is the probability that at most two of the offspring are aa?
MATH1550H: Assignment: Questions: Let’s assume the department of Mathematics of Trent University has 11 faculty members. For i = 0; 1; 2; 3; find pi, the probability that i of them were born on Canada Day using the binomial distributions.
Caselet on McDonald’s vs. Burger King - Waiting time
Generate descriptive statistics. Create a stem-and-leaf plot of the data and box plot of the data.
Problems on Sampling Variability and Standard Error and Confidence Intervals
Estimate the population mean
Conduct a marketing experiment in which students are to taste one of two different brands of soft drink
Find out the probability
LINEAR PROGRAMMING MODELS
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd