A proposal has been submitted to replace a group of assembly workers, each working individually, with an assembly line. The following table gives the individual work elements.

Element Te(min) Immediate predecessors
1 1.0 ---
2 0.5 ---
3 0.8 1,2
4 0.3 2
5 1.2 3
6 0.2 3,4
7 0.5 4
8 1.5 5,6,7

The demand rate for this job is 1600 units/week (assume 40h/week) and the current number of operators required to meet this demand is eight using the individual manual workers.
a) Construct the precedence diagram from the data provided on work elements.
b) Use the largest-candidate rule to assign work elements to stations. What is the balance delay for the solution?

Reference no: EM13297052

Questions Cloud

What will be shape of air-alcohol nd alcohol-water interface : A 10cm diameter vertical tank holds 20cm of water topped with 15cm of ethyl alcohol. The cylinder is rotated about its central axis at a rotation rate of 20 rad/s. (a) What will be the shape of the air-alcohol and alcohol-water interfaces (include ..
Explain glass to be better conductor of heat that styrofoam : Will the recorded temperature change for an exothermic reaction performed in a glass calorimeter be greater or less that that in a styrofoam "coffee cup" calorimeter? Explain. Assume glass to be a better conductor of heat that styrofoam.
What is the implied one-year forward rate : One-year and two-year maturity, default-free, zero-coupon bonds have yields-to-maturity of 7% and 8% respectively. What is the implied one-year forward rate, one year from today?
What is amount still owed : Borrowed from a bank $34,327.08 - The interest rate was 6.50% from July1st 2006 until June 2010 when it was refinanced to 4.75%. The monthly payment paid to bank each month was $480.00 what is amount still owed?
Determine what is the balance delay for the solution : A proposal has been submitted to replace a group of assembly workers, each working individually, with an assembly line. The following table gives the individual work elements. The demand rate for this job is 1600 units/week (assume 40h/week)
Estimate for p is the proportion : The method of maximum likelihood for estimating p states that we should choose the value for p that gives the highest probability of getting what we got on the experiment.
Explain the standard enthalpies of formation : A scientist measures the standard enthalpy change for the following reaction to be -1053.4 kJ : 2H2S(g) + 3 O2(g) 2H2O(g) + 2 SO2(g) Based on this value and the standard enthalpies of formation for the other substances, the standard enthalpy of fo..
Determine what is the maximum daily mass of chloride : The pipe has a flow of 5 m3/s. The stream's chloride concentration just upstream of the pipe's dischage is 12 mg/L, and the runoff pipe's discharge has a chloride concentration of 40 mg/L. Chloride is a conservative substance.
Determine required diameter of each reinforcing steel bar : If the column is subjected to an axial compressive force of 800 kN, determine the required diameter of each reinforcing steel bar so that one-third of the load is carried by the steel and two-thirds by the concrete. Assume Esteel= 200 GPa and Econ..

Reviews

Write a Review

Civil Engineering Questions & Answers

  What percent removal of organic matter

If the BOD5 of the river below the mill outfall must not exceed 5 mg/L, what percent removal of organic matter (BOD5) is required by the mill to meet this requirement?

  Calculate the ph of the solution

A 1.50 L buffer solution is 0.250 M in HF and 0.250 M in NaF. Calculate the pH of the solution after the addition of 0.0500 moles of solid NaOH. Assume no volume change upon the addition of base. The Ka for HF is 3.5 x 10-4.

  What is the rate of evapouration of water

what is the rate of evapouration of water from a reservoir with air temp at 20c and the surface of reservoir is 3000m2.

  Determine the percentages of gravel-sand-silt and clay

The particle-size characteristics of a soil are given in this table. Draw the particle-size distribution curve. X-axis is Particle Size and Y-axis is Percent Finer Particle Size (mm): 0.425, 0.033, 0.018, 0.01, 0.0062, 0.0035, 0.0018, 0.001.

  What is station and elevation of the lowest point on curve

An equal tangent vertical curve conects an initial grade of -3% and a final grade of +1% and is designed for 60mi/h. The PVI is at station 250+50 and elevation 732 ft. What is the station and elevation of the lowest point on the curve

  Formulate a linear program for blend mix

Formulate a Linear Program for Blend Mix at Bluegrass Distillery, The Bluegrass Distillery produces custom-blended whiskey

  Investigate the possibility of environmental problems

Investigate the possibility of environmental problems that faced by the area of disaster.

  At what rate is the string being paid out

a child is flying a kite at a height of 40 ft and the kite is moving horizontally at a rate of 3 ft/sec. if the string is taut, at what rate is the string being paid out when the length of the string is 50 feet.

  Determine depth of water flow in rectangular channel

Find depth of water flow in Rectangular channel, Water is flowing in a rectangular channel whose width is 5m

  Tightening of bolt in the friction grip

What difference does the tightening of bolt in the friction grip joint make to the load at first slip and the failure load.

  Find the optimal solution

The company would like to distribute the songs between the two CDs such that the used space on each CD is about the same. Formulate the problem as an IP, and find the optimal solution.

  What force vector does the angled member apply

The linkage shown is made up of two 3-kg rectangular members (0.4 m by 0.1 m), and is flying through the air. At the instant shown, the vertical member has angular velocity 4 rad/s, and the angled member has angular velocity 1 rad/s.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd