Here is what she suggested to you as a work breakdown structure, including the duration she estimated for each task:
First, you need to meet with fitness center managers at other Personal Trainer locations (5 days).
After these meetings, you can conduct a series of interviews (5 days).
When the interviews are complete, two tasks can begin at the same time: you can review company records (3 days) and observe business operations (8 days).
When you have reviewed the records and observed business operations, you can analyze the BumbleBee accounting software (5 days) and study a sample of sales and billing transactions (2 days).
After completing the analysis and studying the sales transactions, prepare a report for Susan (1 day)
You are excited about the opportunity to practice your skills, and you start to work on the following list.
Tasks
Create a table listing all tasks separately, with their duration.
Identify all dependent tasks, and indicate for each dependent task what predecessor task(s) are required.
Construct a PERT/CPM chart similar to the one in Figure 3-23 on page 86 (see attachment). You can use Microsoft Visio or Microsoft Project or any other project management software to create your chart.
Determine the overall duration of the project, and identify the critical path.