Determine the minimum guy lead length for the pole

Assignment Help Civil Engineering
Reference no: EM13310055

You are an engineer working for a utility company. Your project team is designing the power distribution (overhead wires) in a new subdivision. Shown in the following is the last pole along one of the streets. For this dead end configuration you have the following specifications:
Electric Pole:
Class 2, 100 feet long, with 10 feet buried in earth. Maximum axial load given in column load table.
Stub Pole:
Class 2, 50 feet long, with 10 feet is buried in earth. Maximum axial load given in column load table.
Anchor:
14" PISA with a maximum permitted pull-out load of 17,500 pounds.
Guys:
11k guys that have a maximum permitted tension load of 11,300 pounds.
Wires:
Three primary wires (A, B, and C) - 123.33 AAAC. Each is subject to 2140 pound tension (hence the name ‘high tension wire').

Neutral - #3 Copper. subject to 1180 pounds tension

Finally, you have been instructed to use Class C construction standards. This means a safety factor of 1.1 must be used in your analysis.
The electric pole and the stub pole are at the edges of the roadway right-of-way. The anchor will be outside of the right-of-way and will require the subdivision to purchase land from the neighbouring farmer (who is VERY UNHAPPY about the subdivision in the first place.) Thus, your project leader, knowing that you are an expert in statics, has assigned you the task of determining the minimum guy lead length
(to the nearest foot) for this pole configuration.

TABLE OF COLUMN LOADING LIMITS
50 FOOT UTILITY POLE
(Values based on distance from the top of the pole)
DISTANCE (ft.) MAXIMUM LOAD (lbs.)
1.0 12,600
1.5 13,325
2.0 14,050
2.5 14,775
3.0 15,500
3.5 16,150
4.0 16,800
4.5 17,450
5.0 18,100
5.5 19,175
6.0 20,250
6.5 21,325
7.0 22,400
7.5 23,750
8.0 25,100
8.5 26,450
9.0 27,800
9.5 29,225
10.0 30,650
10.5 32,075
11.0 33,500
11.5 35,625
12.0 37,750
12.5 39,875
13.0 42,000
13.5 44,125
14.0 46,250
14.5 48,375
15.0 50,500
15.5 53,975
16.0 57,450

Reference no: EM13310055

Reviews

Write a Review

 

Civil Engineering Questions & Answers

  What will be discharge delivered from the upper reservoir

A reservoir at elevation 700 ft will supply a second reservoir at elevation 460 ft. The reservoirs are connected by 1300 ft of 24-in cast-iron pipe and 2000 ft of 20-in cast iron pipe in series. What will be the discharge delivered from the upper ..

  Length of the curve-elevation of the curve at station

A vertical curve is to connect two tangents that intersect at station 50+00 and the elevation 500.00ft. The back tangent gradient is -4 percent, the forward tangent gradient is 2 percent, and the elevation of the curve at station 48+50 must equal ..

  Determine what is the saturation wet unit weight of the soil

In an undisturbed soil formation, it is known that the dry soil weight is 115pcf. The specific gravity of the soil particle is 2.75.a) What is the saturation wet unit weight of the soil b) What is the submerged weight of the soil

  Calculate distance up ramp using the work energy theorem

A 58.3 degree inclined plan has a spring with spring constant 23,400 N/m attached at the bottom.A 1.2 kg block is placed on the plane and compresses the spring a distance of 2.4 cm from equilibrium.

  Determine an appropriate plywood thickness and span rating

For a total floor load of 75 psf on 2x floor framing at 24 o.c., determine an appropriate plywood thickness and span rating assuming panels with edge support and panels oriented perpendicular to the framing. Specify the minimum fasterners and spac..

  What surface area in square meters must she cover

A worker is to paint the walls of a square room 8ft high and 12 ft along each side. what surface area in square meters must she cover?

  How much larger should street name be in order to be legible

street nam sizes on the signs at a certain location can be discerned by a person with 20/40 vision from a distance of 300 ft. how much larger should the street names be in order to be legible to a person with 20/50 vision from a distnace of 450 ..

  Total delay and maximum queue length

Determine total delay, maximum queue length, and the time that the 20th vehicle to arrive waits from its arrival to its departure.

  Whether proportional limit is exceeding for either material

To prevent this high compression load from buckling the copper pipe, a solid steel support of 2 1/2 inch diameter is placed inside the copper pipe. The copper pipe is 8.000 inches long. The steel support is 8.0001 inches (exactly 1 mil = 1/1000 in..

  Determine the maximum in-plane shear stress on the wall

a). Determine the state of stresses in the walls and indicate these stresses (including arrows to denote the direction of the stresses) on the element below. b). Then, determine the maximum in-plane shear stress on the wall of the pipe using Mohr's..

  Determine what is the drag coefficient of a 3000-lb car

A 3000-lb car has a maximum speed (at sea level and on a level, paved surface) of 140 mi/h with 16-inch-radius wheels, a gear reduction of 3.5 to 1, and a drivetrain efficiency of 92%. It is known that at the car's top speed the engine is producin..

  Determine what should the sample volume be

The dissolved oxygen of sample water is 1.5 mg/L. At 25 C, the dissolved oxygen of the dilution water is 8.25 mg/L. You are told the BOD5 of the sample is 130 mg/L. You have a target final dissolved oxygen of 3.0 mg/L (give yourself some leeway).

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd