Determine the job cost of project aq

Assignment Help Managerial Accounting
Reference no: EM132556430

Sam Company uses job-order costing system to record and track the costs of its projects. The following information is provided for the decorating projects in January 2020:

                                     Project AQ01                            Project AQ02

Direct labour hours                    300                                       450

Machine hours                           100                                      120

Direct materials                       $108,000                              $150,000

Direct labour cost                      $520,000                             $480,000

There was no work in process at the beginning of January 2020. Actual manufacturing overhead costs were $36,000 for January 2020.

Sam computes its predetermined overhead rate annually on the basis of machine hours. At the beginning of2020, Sam estimated that its total manufacturing overhead would be $900,000, the total direct labour cost would be $6,000,000, and the company would work a total of 40,000 direct labour hours and 5,000 machine hours on all projects.

Required:

Question (a) Project AQ01 was successfully completed and sold on 31 January 2020. Determine the job cost of Project AQ01 and its contract price if the markup percentage of this job is 50%.

Question (b) Assume that the company allocates any underapplied or overapplied manufacturing overhead to work in process, finished goods and cost of goods sold on the basis of 2:2:6, prepare the adjusting entry to show the allocation for January 2020.

Reference no: EM132556430

Questions Cloud

What is the maturity value of the note : On June 8, Williams Company issued an $82,800, 11%, 120-day note payable to Brown Industries. Assuming a 360-day year, what is the maturity value of the note
What are the main benefits of international harmonization : Countries are using different approaches to strengthen auditor independence. What are the main benefits of international harmonization of auditing standards
Project controls and testing : Identify the control objectives and techniques that will ensure the completeness, accuracy, validity, and authorization of transactions
Compute the amount of bond interest expense to be recognized : If Franklin uses the straight-line method of amortization of bond premium, compute the amount of bond interest expense to be recognized on July 1
Determine the job cost of project aq : Completed and sold on 31 January 2020. Determine the job cost of Project AQ01 and its contract price if the markup percentage of this job is 50%.
What is the amount of cash dividends : Assume that 36,383 shares were originally issued and 3,240 were subsequently reacquired. What is the amount of cash dividends to be paid
What is the amount of gain or loss on redemption : Bonds Payable has a balance of $919,000 and Discount on Bonds Payable has a balance of $9,190. What is the amount of gain or loss on redemption
Prepare the cash flows for operating activities : H&M, Inc., Prepare the cash flows for operating activities under the indirect method as it would appear on the statement of cash flows.
How much was the net cash flow from operating activities : There was also a loss on the sale of equipment of $4,471. How much was the net cash flow from operating activities on the statement

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd