Problem P 6-16

A hospital is planning an $8 million addition to its existing facility. The architect has been asked to consider the following design parameters: (1) There should be at least 10 and no more than 20 intensive care unit (ICU) rooms; (2) there should be at least 10 and no more than 20 cardiac care unit (CCU) rooms; (3) there should be no more than 50 double rooms; (4) there should be at least 35 single rooms; and (5) all patient rooms should fit inside the allotted 40,000-square-foot space (not including hallways). The following table summarizes the relevant room data:

SINGLE DOUBLE ICU CCU

Cost per room to build and furnish ($thousands) $45 $54 $110 $104

Minimum square feet required 300 360 320 340

Profit per room per month ($thousands) $21 $28 $ 48 $ 41

How many rooms of each type should the architect include in the new hospital design?

Problem P 6-30

6-30 Sandy Edge is president of Edge File Works, a firm that manufactures two types of metal file cabinets. The demand for the  two-drawer model is 650 cabinets per week; demand for the three- drawer cabinet is 400 per week. Edge has a weekly operating capacity of 1,600 hours, with the two- drawer cabinet taking 1.5 hours to produce and the three-drawer cabinet requiring 2 hours. Each two-drawer model sold yields a $12 profit, and the profit for the three-drawer model is $14. Edge has listed the following goals, in rank order:

Rank 1: Attain a profit as close to $12,000 as possible each week.

Rank 2: Avoid underutilization of the firm's production capacity.

Rank 3: Sell as many two- and three-drawer cabinets as the demand indicates.

Set up and solve this problem as a goal programming model.

Problem 7-18

7-18 A plant engineering group needs to set up an assembly line to produce a new product. The table in the next column describes the relationships between the activities that need to be completed for this product to be manufactured.

(a) Develop a project network for this problem.

(b) Determine the expected duration and variance for each activity.

(c) Determine the EST, EFT, LST, LFT, and slack for each activity. Also determine the total project completion time and the critical path(s).

(d) Determine the probability that the project will be completed in less than 34 days.

(e) Determine the probability that the project will take more than 29 days.

ACTIVITY DAYS IMMEDIATE

PREDECESSORSa m b

Problem 7-18

Activity Pred Optim time (a) Most likely time (m) Pessim time (b) Expected time Variance Standard deviation EST EFT LST LFT Slack Critical?

0.00 0.00 0.00 0.00 0.00 Y

0.00 0.00 0.00 0.00 0.00 Y

Critical path =

Project length = 0.00 days

Project variance = 0.00

Project std deviation = 0.00 days

P(Finish < = 34 days) = #NUM! P(Finish >= 29 days) = #NUM!

Reference no: EM131412479

Questions Cloud

Provide a description of the consumers experience : Identify the title of advertisement, name of product or service, title of publication or name of televisionnetwork.
Categorize different scheduling procedures for various types : Categorize different scheduling procedures for various types of service operations, such as restaurants, hospitals, and airlines.
Capabilities confer sustainable competitive advantage : Use the functional classification and value chain perspectives to identify Harley-Davidson's principal resources and capabilities. Respond to the following: Can Harley-Davidson's resources and capabilities confer sustainable competitive advantage? Wh..
Component of the s-p 500 : Choose a company in a part of the world and domain where you feel at ease with daily quotes available at http://finance.google.com and which issue dividends (e.g. you can select a component of the S&P 500, Nasdaq, SMI (Swiss Market Index) or any Eu..
Determine the expected duration and variance for activity : 6-30 Sandy Edge is president of Edge File Works, a firm that manufactures two types of metal file cabinets. The demand for the  two-drawer model is 650 cabinets per week; demand for the three- drawer cabinet is 400 per week. Edge has a weekly oper..
Politics is driven by how people interpret informaion : Comment on the Debra Stone quote reprinted in the text: "Because politics is driven by how people interpret informaion, much political activity is an effort to control interpretations." What do you think of this idea that even information is politica..
List the endogenous and exogenous variables : List the endogenous and exogenous variables in the Beginning and Ending Balance Sheets, the Income Statement, and the Statement of Cash Flows.
Can your body make glucose from proteins and from fats : Can your body make glucose from proteins? from fats? Which fats are said to be healthier saturated or unsaturated? Why? Which cholesterol is said to be healthier, LDL or HDL? Why?
Write a function that implements such a converter : Write a VDHL code from which this converter can be inferred. Enter N (number of bits) as a GENERIC parameter, and use the closed-form expression obtained above to do the computations. Include simulation results in your solution.

Reviews

Write a Review

Operation Management Questions & Answers

  How would you go about developing a risk matrix

How would you go about developing a risk matrix? Give an example of the kinds of factors that should be evaluated.

  What is the federal governments policy toward transportation

What is the federal government's policy toward transportation?

  Important part of the project execution process

Project monitoring and control is an important part of the project execution process. The project manager should monitor project progress and report project performance to the stakeholders in a timely fashion. I need to understand Earned Value Analys..

  All seven jobs must go through d and e in that sequence ie

you are responsible for an operation that has 12 distinct jobs. seven of those jobs must be processed in two

  What is organizational culture

What is Organizational Culture. Organizational Culture: The set of shared values and norms that controls organizational members' interactions with each other and with people outside the organization

  Provide a detailed justification of your decision

As Greenery's COO, you need to make a recommendation to the CEO about what option Greenery should follow. They can produce in-house, outsource production, or pass on the offer. Provide a detailed justification of your decision using material from ..

  Question 1vance armstrong is making his monthly order every

question 1vance armstrong is making his monthly order every 30 days for a supply of racing tires for the sunshine

  Employees based upon religion-sex or national origin

When may an organization legally hire employees based upon religion, sex, or national origin? Provide an example of a job that would permit such a restriction (one example for each of the three qualifications).

  Assignment on crafting a strategy to fit the business

Assignment On Discussion- Crafting a Strategy to Fit the Business. Can a company like Amazon have a strong business model but a weak strategy. Using the Internet, find Amazon's most recent annual report and peruse its main sections.

  What price should it set

Why will a monopolist's output increase if the government forces it to lower its price? If the government wants to set a price ceiling that maximizes the monopolist's output, what price should it set?

  What is the optimal interval

What is Office Supreme's optimal ordering quantity and optimal associated cost? What is the optimal interval (in working days) between orders?

  Using manuscript speaking and impromptu speaking

You are attending a career college that sponsors a Graduation Luncheon each spring. The luncheon is open to all students who will graduate on May 20th. Alumni of the college also attend the luncheon and give brief presentations about how their academ..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd