A horizontal curve is designed for a two-lane road in a mountainous terrain. The following data are known:
Deflection angle: 40 degrees
Tangent: 436.76
Station of PC: 2695 + 73.89
Side friction factor = 0.12
Superelevation = 8%
Superelevation run-off rate = 1:400
Lane width = 12 ft
Normal crown slope = 2%
Determine the following:
Design speedLength of the curveDegree of the curveStations of the PI and PTStation of superelevation runoff beginsStation of tangent runoutStation where the curve is fully superelevatedStation where the superelevation is 3%
Due to a crash at a railroad crossing, an overpass is to be constructed on an existing level highway. the existing highway has a design speed of 50 mi/h.
You add 100 mg/L of glucose to pure water, then decide that this was a mistake and decide to remove it biochemically before you serve the water to your friends at a cocktail party. To remove the glucose, you seed the water with a harmless bacteria..
Water flows past a triangular flat plate oriented parallel to the free stream. Integrate the wall shear stress over the plate to determine the friction drag on one side of the plate. Assume laminar boundary layer flow.
A four- lane undivided multilane highway ( two lanes in each direction) has 11- ft lanes and 5- ft shoulders. At one point along the highway there is a 4% upgrade that is 0.62 mi long.
How will calculate the surface area of a rectangular open trench Length=100 mtr,Width=.6mtr,Depth= .75mtr.
On a certain highway a -6% grade meets a +2% grade at station 70 + 00, elevation 550.97 ft. An equal tangent vertical curve, 800 ft. long, is to be installed to connect these two grades.
Determine the cycle time for a single engine scraper rated at 21 cy heaped that is used to haul material from a pit to a fill 900 ft away under severe conditions. The average haul speed will be 14 mph and the average return speed will be 20 mph.
Consider two alternative water resource projects, A and B. Project A will cost $2,533,000 and will return $1,000,000 at the end of 5 years and $4,000,000 at the end of 10 years.
A 600 mm long solid steel shaft is to transmit a torque of 30 N-m, G=90 GPa, diameter 15mm. Determine (a) Maximum shear stress, and (b) Angle of twist (phi) at the end.
Blood is flowing through an aorta of 1.0 cm diameter at an average velocity of 50 cm/s. The mean pressure is 100 mm Hg, The blood enters a stenosis where the aortic diameter is 0.5 cm. What is the appropriate pressure at the point of maximum steno..
Light-Voice Controlling System. We are planning to design a new light-voice controlling system. The voices will basically coordinate the crossing of a road by blind people. Suppose the crossing will be operated by two coordinated systems
Determine the maximum and minimum stress intensities in the section.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd