Problem-
There are two Alternative proposals to improve traffic flow in Downtown Bangalore, India. Costs and monetary equivalents of benefits and disbenefits are listed in the Table below. The planning period is n years. Salvage values are zero. The interest rate is X%.
Alternative #1
Alternative #2
Initial road construction cost
$29,800,000
$11,000,000
Road maintenance cost/year
$350,000
$210,000
Improved traffic flow/year
$1,200,000
$750,000
Reduced noise pollution/year
$300,000
$ 0
Improved road safety/year
$460,000
$190,000
Reduced traffic policing cost/year
$120,000
Increased air pollution/year
$55,000
Reduced car idling time/year
$85,000
Determine-
(a) the benefit cost ratio for Alternative 2, if n = 30 and x = 3
(b) the minimum value of n that would make Proposal acceptable if x = 2%
(c) the preferred Alternative, if n = 28 and x=3%
Additional Information-
The problem belongs to Civil Engineering and it is explain about proposals for reducing traffic in Bangalore city. The monetary and cost benefits have been given. The benefit to cost ratio for the 2 proposals, the minimum value for the proposals in addition to the preferred alternative has been calculated in the answer.
determine the value of Po, as a funciton of H, for these two investment alternatives to be equivalent at an interest rate of i=15% per year.
Station 0+00 is at BM which has an elevation of 508.97. During the survey, the backsight (BS) to this monument is recorded as 10.92. The level is then turned to sta 1+48, and the foresight (FS) is recorded as 13.14. Next the level is moved to a new p..
What is the equivalent amount in year 10 of an expenditure of $5,000 in year one, $8,000 in year two, and increasing by $1,000 per year through year 10 Assume the interest rate is 10% per year.
The road has 12-ft lanes. Due toexpensive excavation, it is determined that a maximumof 34 ft can be cleared from the road's centerline toward the inside lane to provide for stopping sight distance.
What is the probability that a drought is more severe than a drought of a return period of once in 50 yr will occur exactly twice in 100 yr
A 100% saturated soil has a void ratio of 1.33 and water content of 48%. Find the unit weight of soil in lb/ft^3 and specific gravity of solids
In an unconfined aquifer having K = 30/m/day, two observation wells, 3km apart, have water levels of 50 and 40 m, respectively, above the base of the aquifer. Determine the rate of flow.
A pile resists the tension developed by three stay cables for a major tent (Membrane) Structure. Assuming no bending is desired in the pile (no resultant horizontal component), what is the magnitude of the force S if the angle \thetaS = 30 degrees
if 25 acres of land recieved 3.5 inches of water from the irrigation district, determine volume of water on the land in acre-ft
Drawdown data from an observation piezometer near a well used for a pumping test with constant pumping rate is plotted on a semilog plot vs. time (the time axis, on the horizontal, is on a log scale).
A hydroelectric facility operates with an elevation difference of 50.0 m with a flow rate of 500 m3/sec. If the rotational speed is 90 rpm, determine the most suitable type of turbine and estimate the power output of the arrangement.
A vertical crest curve has an approach grade +6% and a departure grade -6%. The Vertical intersection point level is 125 m. It is proposed to use a curve 720 m long. Calculate the level at TPl.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd