Determine Critical path
Determine critical path and also need help in finding how to reduce the project time by a number of weeks.
Activity Immediate Predecessor Time (in weeks)A none 4B A 2C A 4D A 3E B,C 5F C 6G D 2H E 3I F,G 5J H,I 7
1. Draw the network diagram.2. Find the critical path.
3. If activities A and J can't be shortened, yet activities B through I can be shortened to a minimum of one week at a price of $10,000 per week, which activities whould you shorten to cut the project by four weeks?
Find and explain the author's ideas. Include specific passages that support the description of the author's point of view.
As an administrator for a medium sized hospital, you also the board of directors have decided to change to a drug dependency hospital from a short term, acute care facility. Explain how would you go about executing this strategy?"
What aspects of the key stakeholder's roles do you need to be aware of when communicating the results and what is your plan to address the possible reactions of key stakeholders to the results?
Will you describe finance and budgeting situations/practices that could be positively impacted by technological solutions.
medicare tied to life expectancy advantages disadvantagesmedicare should be linked to median or average u.s. life
1. what are the various facets of the job of an arbitrator? cite examples of ethical considerations past practice
If you are a non-exempt employee covered by the Fair Labour Standards Act, elucidate how many hours of overtime pay, if any, would you be entitled to? Illustrate what would be the rate.
what would you say to this individual if he or she was part of a team you were working on for the development of a new product?
Solve the equation
Explain when firms should discount projects using the cost of equity. When should they use the WACC instead? When should they use neither?
important information about scenerios for organizational psychology1. organizations often consider new employees to be
To help Amanda secure a loan for the car, Ted, a friend, agreed to pay the loan should Amanda default. Ted's promise to pay the loan is a collateral promise. His promise must be in writing to be enforceable.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd