Reference no: EM131366997
Tom Schriber, a director of personnel of Management resources, Inc. is in the process of designing a program that its customers can use in the job finding process. Some of the activites include preparing resumes, writing letters, making appointments to see prospective employers, researching companies and industries, and so on. Some of the infromation on the activites is shown in the following table:
Days Immediate
Activity a m b Process
A 8 10 12 -
B 6 7 9 -
C 3 3 4 -
D 10 20 30 A
E 6 7 8 C
F 9 10 11 B, D, E
G 4 7 10 B, D, E
H 14 15 16 F
I 10 11 13 F
J 6 7 8 G, H
K 4 7 8 I, J
L 1 2 4 G, H
(A) Construct a network for this problem.
(B) Determine the expected time and variance for each activity
(C) Determine ES, EF, LS, LF and slack fore ach activity
(D) Determine the critical path and project somple completion time
(E) Determine the probability that the project will be finsihed in 70 days or less
(F) Determine the probability that the project will be finished in 80 days or less
(G) Determine the probability that the project will be finsihed in 90 days or less
|
Advantages and limitations of portfolio analysis
: Advantages and limitations of portfolio analysis. What are the things a researcher should do and keep in mind while taking consent from an individual for research and innovative treatment?
|
|
Company specializing in climate-controlled pet houses
: Juki Mara is Dallas based company specializing in climate-controlled pet houses. According to the company’s VP of Operations, their market segments basically compromise of high-end customers who are either dog or cat owners and who want to pamper the..
|
|
According to the research on the mcclelland theory
: According to the research on the McClelland theory of needs. Remember, McClelland believes that individuals are motivated by achievement, power, and affiliation, yet they tend to favor one over the others. After reviewing and researching the theory, ..
|
|
Are all of the elements of a contract present in this case
: Susan, a wealthy widow, invited an acquaintance, John, to her home for dinner on a specific date at a specific time. Jonathan told Susan that he would be delighted to come to dinner and, eager to impress Susan, spent lavishly in preparing for the eve..
|
|
Determine critical path and project somple completion time
: Tom Schriber, a director of personnel of Management resources, Inc. is in the process of designing a program that its customers can use in the job finding process. Determine the expected time and variance for each activity. Determine ES, EF, LS, LF a..
|
|
How managing human capital
: How MANAGING HUMAN CAPITAL course can assist you in achieving further professional goals. What is the most valuable concept you can learn by doing MANAGING HUMAN CAPITAL subject?
|
|
Explain the purpose of background investigations
: Evaluate the relationship between the development strategy in one hand and recruiting and selection ? Explain why employee training is important? Also discuss Why career development is valuable to organizations? Explain the purpose of background inve..
|
|
What issues in channel conflict might arise
: What issues in channel conflict might arise from Procter and Gamble’s special arrangements with Amazon.com? Would you recommend that Procter and Gamble use any mode of transportation other than trucks to transport cartons to retailers?
|
|
Two type of turkey cutlets for sale to fast-food restaurants
: The Wild Turkey Company produces two type of turkey cutlets for sale to fast-food restaurants. Each type of cutlet consists of white meat and dark meat. Cutlet 1 sells for $4 per pound and must consist of at least 70% white meat. Determine how maximi..
|