Reference no: EM132245049
Jack and Alien’s new gaming laptop.
Jack Daniel is an expert in digital signal processing and was promoted to Senior Design Engineer just two years after Alien whose company motto is “For gamers by gamers”. After serving as a Senior Design Engineer for two years, he was promoted to Project Manager and asked to oversee a product development project involving a relatively minor product line extension one of Alien’s gaming keyboards.
Alien had a range of existing gaming laptops and gaming peripherals that are distributed through a network of value-added resellers. After completing the gaming keyboard product line extension project about nine months ago, Jack was asked to serve as the project manager for a project to develop a new line of ”Superlite” gaming laptops. This was the first time he was to lead a major strategic project for the organization so Jack wasted no time in planning the project. Based on the success of the product line extension project, he decided to modify the work breakdown structure he had developed for the product line extension project and apply it to this new project to develop a new line of notebook computers. He recalled the weeks of planning that went into developing the work breakdown structure for the desktop product line extension project. The entire project team had been involved, and that was a relatively straightforward product line extension. The current project was more complicated, and there simply was not sufficient time to involve all team members. What was the point of wasting valuable time and resources to re-invent the wheel? Jack thought between his experience and the suggestions made by the Vice-President he has more than enough information to plan the project.
After modifying the work breakdown structure, Jack scheduled a meeting with the Vice-President of Product Development to discuss staffing the project. As was typical of other product development projects at Alien, Jack and the Vice-President agreed that the project should be housed within the engineering division. In his capacity as project manager, Jack would serve as liaison to other functional areas such as marketing, purchasing, finance, and production. However thought since they had finished the desktop product line extension project they should have plenty of spare capacity for the new line of notebook computers. Jack was concerned that half the engineers had already been assigned to other projects but thought that if everything worked out well it should still work.
As the project progressed, it continued to slip behind schedule. Jack found it necessary to schedule a meeting each week to address how unanticipated activities would be completed. For example, last week the team realized that no one had been assigned to design a light system to allow the screen to attach and detach the base so that it could be used as a touch screen.
Indeed, Jack found himself increasingly in crisis mode. For example, this morning the manufacturing group sent a heated email to Jack complaining about his conflict management style which was described as aggressive. The manufacturing group noted that they just learned of the notebook computer project and based on the design presented to them, they would not be able to manufacture the printed circuit boards because of the extensive amount of surface mount components required. Jack responded to this message by noting that the engineering group was doing its job and had designed a state-of-the-art notebook computer. He added that it was the manufacturing group's problem to decide how to produce it. He thought some people just do not have a "can do" attitude wanted to spend too much time talking about problems.
Just as troubling was the crisis that had occurred earlier in the week. The Vice-President of Product Development had requested that the notebook computer incorporate a new type of interface that would allow the notebook computer to synchronise information with the new portable playing platform Alien was about to introduce. Jack explained that incorporating new interfaces for high speed synchronise of large would delay the introduction by a minimum of several months. Nevertheless, the Vice-President was adamant that the change be made. The Vice-President of Product Development said to Jack it was pretty obvious from Alien's President's speech last week that all Aliens products would interface with each other and expressed concern that Jack seems to be losing his "can do" attitude and wanting to spend too much time talking about problems. The Vice-President of Product Development thought it was time to get a new project manager. He felt Jack did not know how to play the game and was disappointed that Jack had messed up such a simple project.
Questions:
1. Does Jack Daniel show the competencies' of a good project manager? Describe the characteristics of a good project manager and compare Jack to these characteristics using frameworks discussed in the course.
2. “Jack’s great strength is his ability to manage teams.” Do you agree or disagree? Use relevant concepts from the course and specific examples from the case to justify your answer.
3. How could the problems facing Jack been avoided or lessened if good project management practices and auditing processes had been used. Identify four problems and how these could have been addressed using specific concepts and frameworks covered in the course. Clearly define the problem and provide specific examples of how specific concepts and frameworks covered in the course these could have been used to lessen the risk or impact of this problem.