Define the critical chain and explain the concept of ccpm

Assignment Help Operation Management
Reference no: EM131260364

QUESTION 1. Currently the project management landscape includes traditional project management, agile project management and a number of other models and variations. The traditional model is good for projects that are well defined and goals are clear. Additionally few changes are expected and much of the project effort is known and well supported by tools, templates, and team member skill sets.

Indicate unique factors that define traditional project management efforts and list strengths of the Traditional linear PMLC.

QUESTION 2. When is it appropriate to use Agile Project Management (APM)?

QUESTION 3. Define the Critical Chain. Explain the concept of CCPM and how resources drive the actions of the Project Manager.

QUESTION 4. Writing the final report provides a history of project. The report includes initial planning efforts, milestone achievements, progress against plan, impediments to project and so on.

-Outline the major areas of a final report.

-Also include a paragraph on project team recommendations - what information is included and how might the information be used.

QUESTION 5. Pick a job/project that you are familiar with similar in nature, time, and scope to building a 20' by 20' barn that includes electrical service and concrete floor. Construct a Work Package Assignment Sheet that list Work Package Name and Number, Start and Finish schedule for each package. Also include Resources required to complete each package.

QUESTION 6. JLB Construction has been contracted to provide a security enclosure for a Water Distribution facility for a major metropolitan area. The structure is in the shape of a pentagon and is a wall. One side of the wall contains a secure gate for exit and entry. Total project cost is estimated at 1 million dollars. The wall will be 10 feet tall with securing system on top of wall. Wall is 12 inches think with a foundation six feet deep. Gate area allows for the entry of all vehicles including construction vehicles. The cost to construct each side of the wall is essentially the same. Initial construction went pretty well - on schedule and with current spending at 700,000. Currently the Gate wall and two additional walls have been constructed.

Calculate current values.

What is the plan value (PV)?

What is the current earned value (EV) for JLB Construction to date?

What is the actual cost to data (AC)? What is the cost variance to date (CV)?

Show all calculations.

QUESTION 7. Controlling a project requires analyzing efforts and providing reports that provide status of aspects of the project. Exception reports are noteworthy across the list of reports. Define exception report? Note who exception reports are written for? How long is the typical exception report? Going back to our EV calculations for the pentagon wall: Write a half page exception report on the current issues with the Wall Project.

QUESTION 8. Compare and contrast - Traditional Project Management (TPM) and Agile Project Management (APM) in general and across the five process groups?

QUESTION 9. Characterize the scoping phase of an adaptive PMLC project? How is the scoping phase of TPM different than the scoping phase of an adaptive PMLC project?

QUESTION 10. Closing a Project - Closing the project is routine once you have the client's agreement that all deliverables have been met according to scope outlined in project contracts.

Closing the project consist of six major steps.

List and define each step.

Include typical activities and documents associated with the steps.

Reference no: EM131260364

Questions Cloud

What are the key ingredients of lean : What are the key ingredients of Lean, as identified at Alaska Airlines? -  As an initial phase of a kaizen event, discuss the many ways passengers can be loaded and unloaded from airplanes.
What is a relational database : What is a relational database? What are the advantages of a relational database over a file system?
Compute the corresponding angle of twist for steel : Determine the largest torque that can be safely applied to the rectangular steel bar if the maximum shear stress is limited to 120 MPa.
What is an associative entity : 1. What is an associative entity? When must a many-to-many relationship be modelled as an associative entity? Provide some examples demonstrate this issue.
Define the critical chain and explain the concept of ccpm : Characterize the scoping phase of an adaptive PMLC project? How is the scoping phase of TPM different than the scoping phase of an adaptive PMLC project?
Find the maximum shear stress in the tube : A steel tube with the cross section shown carries a 50-kip in. torque.
Strategic plan for the corporations divisions : To feel confident that all of the employees in your strategic planning team understand all that you have taught them, you require each to prepare a streamlined version of the key elements of a strategic plan.
What amount of family federal income tax savings : Brian is an 85 year old single taxpayer who is in the 39.6% federal income tax bracket. As part of his estate planning strategy, he gifted General Electric Corporation bonds to his 30 year old grandson, Casey, who is single and in the 25% federal inc..
Layer of the ethernet protocol : Explain three functions of data encapsulation in the MAC sub layer of the ethernet protocol?

Reviews

Write a Review

Operation Management Questions & Answers

  Decision makers in queuing situations attempt to balance

Decision makers in queuing situations attempt to balance

  Completes processing of loans

A bank handles loans. Management knows the bank receives 40 applications per week on average, which is equivalent to $20 million. It knows that it completes processing of loans in 25 business days on average. How many loans are typically in process?

  Explain four of the various ways groups can make decisions

Explain four of the various ways groups can make decisions. For each of your chosen methods, explain its advantages and disadvantages.

  Customers arrive at the lobby of the exclusive

Customers arrive at the lobby of the exclusive and expensive Ritz Hotel at the rate of 40 per hour (Poisson distributed) to check in. The hotel normally has three clerks available at the desk to check guests in. The average time for a clerk to check ..

  Identify the symptoms

This report should be double spaced, in narrative format, 12-point font, and three to four paragraphs in length excluding the title page and reference page.

  Contract administration during control procurement phase

Which type of contract requires the least contract administration during control procurement phase? Which type requires the most? Why?

  Describe how these sources might be used

What are some secondary sources of information that might be used to conduct research into this topic? Describe how these sources might be used. Describe a method you could use to gather primary research data about the topic.

  Pret a manager puts peer pressure to work

Read case study, "Pret A Manager Puts Peer Pressure to Work" located at the end of chapter 10 of Principles of Management text. What are the benefits of creating a team whose members hold hiring power over potential new employees? What are the potent..

  Does this apply to the consulting industry

Evans & Wurster assert which Information Technology might enable some to escape the historical trade-off between richness also reach. Does this apply to the consulting industry.

  Write a grievance procedure document outlining

Write a grievance procedure document outlining all eight steps for a meeting or an arbitration hearing and be sure to cite your sources.

  What is the typical profile of a venture champion

What is the typical profile of a venture champion? What do we know about them? What makes the successful?

  Forecasted demand over the planning horizon

Forecasted Demand over the planning horizon is as follows: Month 1 2 3 4 5 Demand 250 250 375 400 450 Regular production cost is $2 per unit. Regular production capacity is 300 units. Beyond 300 units, the company must subcontract, at a cost of $3 pe..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd