Decision based on expected monetary value criterion

Assignment Help Operation Management
Reference no: EM13845545

The product design group of Iyengar Electric Supplies, Inc., has determined that is needs to design a new series of switches. It must decide on one of three design strategies. The market forecast is for 200,000 units. The better and more sophisticated the design strategy and the more time spent on vague engineering, the less will be the variable cost. The chief of engineering design, Dr. W. L. Berry, has decided that the following costs are a good estimate of the initial and variable costs connected with each of the three strategies:

a) Low-tech: A low-technology, low-cost process consisting of hiring several new jurior engineers. This option has a fixed cost of $45,000 and variable-cost probabilities of .3 for $.55 each, .4 for $.50, and .3 for $45.

b) Subcontract: A medium-cost approach using a good outside design staff. This appraoch would be a fixed cost of $65,000 and variable-cost probabilities of .7 of $.45, .2 of $.40, and .1 of $.35.

c) High tech: A high-technology approach using the very best of the inside staff and the latest computer-aided design technology. This approach has a fixed cost of $75,000 and variable-cost probabilities of .9 of $.40 and and .1 of $.35.

What is the best decision based on an expected monetary value (EMV) criterion? (Note: We want the lowest EMV, as we are dealing with costs in this problem.)

Reference no: EM13845545

Questions Cloud

Managing change in guiding an organizational change : How can a leader use the Cummings and Worley's five dimensions of leading and managing change in guiding an organizational change?
Formulate linear program to help them minimize labor costs : Rachel Nolan surveyed her employee schedule for In a Day Drycleaners. She was having trouble keeping labor costs down while meeting demand. In a Day Drycleaners guarantees to have their customer's clothes cleaned within 24 hours. Given the worker req..
Successfully apply quantitative analysis in management : Discuss the complexity of problem definition and the importance of accurate data to successfully apply quantitative analysis in management.
Intuit developed the wildly successful quick books : Intuit developed the wildly successful quick books: Simple Start Edition, Which eliminated all accounting jargon. Could this idea be the foundation of a new version of Intuit's top-selling Turbo Tax software, which removed all tax accounting jargon f..
Decision based on expected monetary value criterion : The product design group of Iyengar Electric Supplies, Inc., has determined that is needs to design a new series of switches. It must decide on one of three design strategies. The chief of engineering design, Dr. W. L. Berry, has decided that the fol..
Difference between an object and a class : difference between an object and a class
Intuits customer-driven development process : Which do you prefer: Intuit's customer-driven development process, where hundreds of employees and managers are sent to consult with customers in their homes or places of business, or Microsoft's process of using professional anthropologists to do su..
Part of the application software development process : Should large software development companies like Microsoft, as well as the thousands of small independent software companies, duplicate intuits’ unconventional thinking and acceptance of failure as part of the application software development process..
Discuss government methods to combat discrimination : Discuss government methods to combat discrimination in employment services. What are the challenges facing recruitment for public and nonprofits organizations today?

Reviews

Write a Review

Operation Management Questions & Answers

  What cost improvement can be expected from the new location

Based on information for the current years, is Kansas City the best location for a warehouse? If not, what are the coordinates for a better location>? What cost improvement can be expected from the new location?

  Find the total of all labor and non-labor costs

Prepare a graph that illustrates the project budget over time. This is the Cost Baseline. Find the total of all labor and non-labor costs. This is your Budget at Completion (BAC)

  Compare and contrast any two traditional training methods

Compare and contrast any two traditional training methods. Of the two, evauate which you feel is the more effective approach.

  Discuss the pros and cons of updating product design

What are the pros and cons of updating the product design based on incrementalism? Besides the iPod, identify at least two products that use this approach for product design

  Strategy to assembly line that wheeled coach currently uses

Why do you think major auto makers do not build ambulances? What is an alternative process strategy to the assembly line that Wheeled Coach currently uses? Please justify your recommendation.

  Identify a product offered within an industry

Identify a product offered within an industry. Using Macro-trend analysis from readings identifies, discuss also analyze macro-trends that may impact industry over next five years.

  Measures of productivity and multifactor productivity

In forecasting, explain how you would determine which variable is the independent variable, and which is the dependent variable? Regarding productivity what is the difference between measures of productivity and measures of multifactor productivity? ..

  Logistics strategy connect to overall corporate strategy

Do you agree or disagree that return on assets is a good way to examine operational efficiency? Why? How does logistics strategy connect to overall corporate strategy? Is it a one-way or two-way connection? Do you think corporate cultures are relevan..

  Creating a solid financial plan

Discuss the best way to leverage a breakeven analysis when defining a business strategy.

  Design logic for a program that merges two files

Each file is in student ID number order. Design logic for a program that merges 2 files into 1 file containing a list of all students in district, maintaining student ID number order.

  Transformational change management plan

You will create an entire Transformational Change Management Plan for a medium-sized public company that has lost business to a competitor that has chosen to outsource much of its production operations.

  Precise engineering corporation has a contract with quik

Precise Engineering Corporation has a contract with Quik Mart Stores to provide customized software for Quik's inventory control system. Retail Outlets, Inc, Quik's competitor,

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd