Following are data reporting progress on a project. Work on all tasks contained in the table is scheduled to be complete as of the day of the report.

 

Budget

Begun?

Complete?

Actual cost

Earned Value

Task A

3,100

Yes

Yes

3,100

 

Task B

4,000

Yes

Yes

4,500

 

Task C

2,500

Yes

Yes

2,250

 

Task D

4,000

Yes

No

3,500

 

Task E

3,500

Yes

Yes

4,000

 

Task F

2,500

No

No

0

 

1) Using the 50-50 Rule, what is earned value for this project?

2) Using the 0-100 Rule, what is earned value for this project?

3) Note the discrepancy of earned value figures when using the 50-50 Rule and 0-100 Rule. Why is there a discrepancy? Which Rule should we use? Explain your rationale.

4) Using the 50-50 Rule earned value computation, what is schedule variance for the project as reported?

5) What is the schedule performance index (SPI)?

6) Using the 50-50 Rule earned value computation, what is the cost variance for the project as reported?

7) What is the cost performance index (CPI)?

8) If the total budget for this project is 50,000, use CPI to compute estimate at complete (EAC).

9) Using the earned value information garnered from the above table, provide your boss a brief status report on project progress to date. Also, provide projections for future status.

Reference no: EM131025769

Questions Cloud

Determine which line is parallel perpendicular or neither : Determine whether the graphs of the pair of equations are parallel, perpendicular or neither.
Which transformer is better : Two transformers, A and B, are both suitable. While both transformers have the same efficiency at peak load, most of the loss in A is due to core loss, and most of the loss in B is due to the resistances of the coils. From the standpoint of operat..
Issue to fund the capital investment under consideration : Suppose your company needs to raise $10 million to construct a new office building at an expanded manufacturing site. As CFO, you plan to raise the money by selling 30-year $1,000 par value bonds with a coupon rate of 6% which is the Yield in Maturit..
Determine the rms values of the currents and voltages : Consider the circuit shown in Figure which has Rs = 0.5Ω, RL = 1000Ω, and N1/N2 = 0.1. Determine the rms values of the currents and voltages with the switch open.
Data reporting progress on a project : Following are data reporting progress on a project. Work on all tasks contained in the table is scheduled to be complete as of the day of the report.
The firm recently announced that all future dividends : Bug Buster just paid its annual dividend of $1.25 a share. The firm recently announced that all future dividends will be increased by 3 percent annually. What is one share of this stock worth to you if you require an 11 percent rate of return? Jackso..
Solve this model using graphical analysis : Solve this system of equations using Matrix. Show all Matrixes and reduce to row echelon form. Do not use decimals, use fractions.
How is the core material selected to minimize the power loss : Suppose we have an ac current flowing through a coil wound on an iron core. Name two mechanisms by which energy is converted to heat in the core material. For each, how is the core material selected to minimize the power loss? How does each power ..
Investors expect the market rate of return : Investors expect the market rate of return this year to be 15.00%. The expected rate of return on a stock with a beta of 1.3 is currently 19.50%. If the market return this year turns out to be 12.80%, how would you revise your expectation of the rate..

Reviews

Write a Review

Business Management Questions & Answers

  Compare goals to program of study mba

Describe how these goals in this assignment are or are not better or clearer as a result of following the SMART model.

  Analysis of the vioxx drug case

This project needs that we submit an eight-fifteen page PowerPoint Presentation on the Viox Drug Case, and the use or misuse of this drug.

  Which of the following is a property of a coalition

Whereas distributive bargaining is often characterized by mistrust and suspicion, integrative negotiation is characterized by which of the following?

  Intentional and unintentional torts

Warrant: What law supports your answer? Include case law when possible     and/or cite the source from the textbook.  Rebuttal:  If there is a counter argument or a gray area you are concerned with, please include it in the rebuttal.  1. Intentional ..

  Strategic planningperformance managementjournal article

strategic planningperformance managementjournal article analysisrequest1. the number of words more than 600 the more

  Merit paywhat is merit pay do you think its a good idea to

merit paywhat is merit pay? do you think its a good idea to award employees merit raises? if yes why? if not why

  Discuss factors that affect the exchange rate

Discuss factors that affect the exchange rate

  What do you see as the role of the business leaders to

what do you see as the role of the business leaders to sustain change and usually you will find naysayers...how do you

  Discuss the difficulty with making assumptions

Discuss the difficulty with making assumptions in a negotiation and why information is important to a successful negotiation process for both sides. Also, how can creative thinking, building of trust, and making appropriate concessions help those..

  Techniques used in workplaces for loading

Discuss the  techniques used in workplaces for loading or leveling resources? Did these techniques work?

  Introduction to the u.s. social security system

Contrast of the systems objective differences between the systems and evaluation of the current U.S. system against the other system (subjective analysis)

  Analyze the consequences of standing up

Explain an instance when you stood up and spoke out for what was right even though you were in the minority or were greatly outnumbered.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd