Critical path to be taken for project completion

Assignment Help Operation Management
Reference no: EM13824671

Consider a project which consists of six activities. The precedence relationships and activity times are as follows:

Activity

Preceding Activities

Time (Days)

1

 

16

2

 

30

3

1

15

4

2

5

5

1

5

6

3, 4

5

What is the critical path for completion of the project?

A. 1 → 3 → 6

B. 2 → 3 → 5

C. 2 → 4 → 6

D. 1 → 2 → 4 → 6

Additional Requirement

This question belongs to Operations Management and it describes about the critical path for completing a project.

 

Reference no: EM13824671

Questions Cloud

Problem regarding incorporation of a private company : James and Lulu, two young businessmen, plan to form a proprietary limited company to operate a restaurant. The company is to be called 'Wonder Taste Pty Ltd' ('Wonder Taste').
Critical path to be taken for finishing a project : Critical Path To Be Taken For Finishing A Project
What should your audience learn from the lesson plan : What should your audience learn from the lesson plan? How does it relate to the course and program outcomes? How will this lesson plan help students in their career or in real-life situations?
Calculate the return on equity ratios for the years : This problem belongs to Accounting and it discuss about calculating return on equity, return on assets, net profit margin, gross profit margin, current ratio, acid test ratio, etc and writing a report based on the analysis of the ratios
Critical path to be taken for project completion : Critical Path To Be Taken For Project Completion
What are the ways in which shortfalls of online initiatives : What do you believe are the most beneficial aspects of online, hybrid, and emerging web-based initiatives? What are the ways in which the shortfalls of online, hybrid, and emerging web-based initiatives can be avoided?
How do these control lines actually become asserted : The ALU has various control lines that determine which operation to perform - "How do these control lines actually become asserted?"
Calculation of ratio of prevention of costs to sales : Calculation Of Ratio Of Prevention Of Costs To Sales
Overview of us export administration regulation : Provide an overview of the U.S. Export Administration Regulation (EAR) and describe the concerns your organization may have with an export of IT equipment such as the router and server you are preparing to send.

Reviews

Write a Review

 

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd