Based on the material covered in class and using the following information about the activities of a project, please identify:
1. the shortest amount of time in which the project schedule can be crashed without exceeding $7K and
2. the project critical path that resulted from crashing the project
Activity
ID
Predecessor
Estimated Optimistic Time
Estimated Most
Likely Time
Estimated Pessimistic Time
Reduction
Time
Goal
Normal Costs
Costs of Reduction
a
-
15
20
85
10
$1,000
$867
b
25
40
235
$400
$262
c
60
100
500
140
$347
d
a, b
30
125
$800
$560
e
45
50
145
$200
$120
f
220
65
$100
$53
g
d, f
130
$1,600
Notes:
Under the less than open-trust conditions, decision makers often spend their time mostly on analyzing their trading partner's credibility, reliability and trustworthiness, rather than optimizing their operations. What is our opinion?
Select two sets of products from your daily diet such as butter/ salad dressing and find similar products that use fat substitutes. Make a list of all the fat substitutes that you find listed on the ingredient labels of the products.
QUESTION What alternative first steps could you use instead of value stream mapping to gain a solid baseline prior to innovating the process?
Based on your own research on the use of e-commerce/e-procurement in the public and private sectors, what are those elements that you consider to be unique to each?
Examine the supply chain of an existing service or manufacturing organization, and justify two to three competitive advantages that the service or organization gains by utilizing the supply chain. Give specific examples to support your rationale.
Find a level workforce plan that uses overtime and the minimum amount of under time (idle time for workers) possible. Overtime can be used to its limits. What is the total cost of this plan and plan for a chase strategy to with variable workforce ..
How do you see the main principles of project management aiding the operations manager/manageress in introducing change to the process/system
Explain the ratio of surface area to volume of cells and why cells can only achieve a certain size and why multicellularity is advantageous compared to unicellularity.
Consider the tetrapeptide Met-Trp-Ser-Arg.
What are the unspoken rules that give Toyota its competitive edge and how do they make it possible for the company to change and improve performance without major disruption?
Topic: Analyze key parameters of a company's supply chain operations, suggest improvements, and predict the operational and economic impact of the changes.
List all the elements that make up the human body. Answers must be in alphabetical order.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd