Critical path activities and their time variances

Assignment Help Operation Management
Reference no: EM13824693

Below is a table of activities required to finish a project:


Activity

Optimistic

Most Likely

Pessimistic

1

19

20

26

2

4

5

6

3

6

6

6

4

3

9

10


In calculating activity times for the project, which one of the following statements is correct?

A. Activity 1 will have the lowest variance

B. Activity 2 will have a variance of 0.11

C. Activity 3 will have the highest variance

D. Activity 4 will have a variance of 0.361

Additional Requirement

In here this question belongs to the operations management and it defines about the activities and their variance in time estimate.

Reference no: EM13824693

Questions Cloud

Preparing reconciliation statement with budgeted profit : This question relates to Accounting and it discuss about preparing reconciliation statement with budgeted profit and actual profit and commenting about inter-relationships between variances
What does the bond currently sell for : A given bond has 5 years to maturity. It has a face value of$1,000. It has a YTM of 6% and the coupons are paid semiannually at a 10% annual rate. What does the bond currently sell for?
How large will your retirement account : Planning to make monthly deposits of 100 into a retirement account that pays 12 percent interest compounded monthly. if your deposit will be made one month from now, how large will your retirement account be in 17 years
Discusses about a minor hired a car : West was 17 years of age & obtained his driver's license. He went to Drive-Yourself Ltd., showed his license, and signed for the hiring of a car.
Critical path activities and their time variances : Critical Path Activities And Their Time Variances
Describe the criteria that are used by each agency : Examine and explain what is required by each agency. Describe the criteria that are used by each agency. Explain how often reviews are conducted by each agency.
Identify critical stakeholder who are affected by curriculum : Identify the critical stakeholders (internal and external) who are affected by the curriculum. Evaluate any theories, models, and/or best practices used by the institution's curricula to assess needs.
Planet wishing to analyze the english language : Suppose you did not know English and were a linguist from another planet wishing to analyze the English language. Be creative with the idea that you are from another planet, but support your responses with references from your book and other sources.
Analyze impact of this demand on your career as an educator : Analyze the impact of this demand on your career as an educator. Discuss the benefits and pitfalls of teaching online.

Reviews

Write a Review

 

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd