Reference no: EM13964454
Cost Estimation After carefully analyzing the data flow diagram, you, the project manager, would like to find out the system's TAFP. You have determined that the project involves implementing ten user inputs (4 with medium complexity and 6 high complexity); six user outputs (2 with high complexity and 4 with low complexity); three queries (all low complexity); and one database file (of high complexity).
a. Use the worksheet to find the TUFP. If the project complexity is estimated as 40, what is the TAFP?
b. Suppose you use VB.NET to implement and the project type is embedded. Find the estimated duration of the project. What is the minimum number of full-time staff? 2. Task Scheduling Using the following task duration and dependency information
Task T7 T8 T9 T10 T11 T12 T13 T14
Duration 3 4 2 7 10 4 7 2
Wait for T7 T7, T9 T10 T11 T8, T11 T12, T13
Create an activity network and identify the critical path. How long will the project at least take? Up to how long can T8 be delayed without affecting the overall project schedule?
|
Essay on letters from an american farmer
: Instructions: Your first essay is an analysis of a topic or theme from J. Hector St. John de Crevecouer's book, Letters from an American Farmer. Your essay should be 3 to 5 pages in length. Please use 12 point font and double-spacing. Your only so..
|
|
The new finance head of a division that reports
: The new finance head of a division that reports to you has just sent you his first proposed budget at the company. Walk through some of the things you are going to review and ask him questions about, especially since this is the first time you are se..
|
|
Used non-regularly spaced appointment intervals
: From personal observations or experience, provide an example where you have seen where service operations have used non-regularly spaced appointment intervals. Did you feel it worked reasonably well? Please explain.
|
|
Find and describe an example of a real-world auction
: What are the differences between your real-world example and the textbook models, and what factors would the bidders need to consider when modifying their bidding strategy to account for the differences?
|
|
Create an activity network and identify the critical path
: Cost Estimation After carefully analyzing the data flow diagram, you, the project manager, would like to find out the system's TAFP. Create an activity network and identify the critical path. How long will the project at least take? Up to how long ca..
|
|
Constitute a reasonable approach to patient scheduling
: Doctors’ and dentists’ offices frequently schedule patient visits at regularly spaced intervals. What problems does this create? Can you suggest an alternative approach to reduce these problems? Under what circumstances would regularly spaced appoint..
|
|
Four factors as they apply to the organization and market
: After doing some research on Porter’s Diamond of National Advantage (in addition to the Huff text, p. 241 and the Document reading), apply the diamond to an organization and an international market where the organization currently does business. Summ..
|
|
Guided analysis-suffering worksheet
: Address the following questions, responding to each one directly below the question. Your total word count (including all questions and your answers) should be between 750-1,000 words.Include a reference page.
|
|
Successful implementation of different types of strategy
: Consistency is the key for the successful implementation of different types of strategy.’ Evaluate this statement with reference to the two generic business - level strategies — cost leadership and differentiation.
|