Crashing an activity on a critical path

Assignment Help Operation Management
Reference no: EM131741414

1. In project management, crashing an activity on a critical path:

a) never impacts the critical path

b) may change the critical path

c) will change the critical path

2. In project management, crashing an activity on a critical path by one time period:

a) may decrease the project duration by one time period

b) will descrease the project duration by one time period

c) may increase the project duration by one time period

3. A PERT project having an expected project duration of 20 days, with a SD of 5 days, has a probability of approximately _____ of being completed in more than 25 days.

a) .50

b) cannot estimate based on the infromation provided

c) .16

4. A PERT project having an expected project duration of 20 days, with a SD of 5 days, has a probability of approximately ______ of being completed within 25 days.

a) .84

b) .95

c) cannot estimate based on the information provided.

5. Decision trees

a) must begin with a chance node

b) are limited to three decision stages

c) none of the above is true

Reference no: EM131741414

Questions Cloud

Structuring occurs in which step of the decision analysis : "structuring" occurs in which step of the decision analysis process? Dealing with "uncertainty" occurs in which step of the decision analysis process?
Wrong guitar to him and refuses to honor the check : Tim later discovers that Strings delivered the wrong guitar to him and refuses to honor the check.
The slope in linear regression equation indicates : A negative value for the slope in a linear regression equation indicates. The coefficient of determination.
Discuss the problems exporters have with letters of credit : Discuss the problems exporters have with letters of credit
Crashing an activity on a critical path : In project management, crashing an activity on a critical path:
Marketing strategies of low cost carries- legacy airlines : Discuss the business and marketing strategies of low cost carries versus legacy airlines.
Accountable for each of these four activities : Prepare a RACI chart for the four WBS activities listed. You decide that one person should be accountable for each of these four activities,
About promoting products in different markets : Marketing in business is about promoting products in different markets.
What is meant by staggering the terms of board members : What is meant by staggering the terms of board members? How might the staggering help with continuity?

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd