Your project to obtain charitable donations is now 30 days into a planned 40-day project. The project is divided into 3 activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 25 days of the project and to bring in $25,000. Even though we are 30 days into the project, we still see that we have only 90% of this activity complete. The second activity relates to company donations and is scheduled to run for 30 days starting on day 5 and extending through day 35. We estimate that even though we should have (25/30) 803% of this activity complete, it is actually only 50% complete. This part of the project was scheduled to bring in $150,000 in donations. The final activity is for matching funds. It is scheduled to bring in and additional $50,000. So far $175,000 has actually been brought in on the project.
Calculate the schedule variance, schedule performance index, and cost (actually value in this case) performance index. How is the project going? Hint: Note that this problem is different since revenue rather than cost is the relevant measure. Use care in how the measures are interpreted.
which internal parties and external parties must procurement consult with when considering whether to produce a product
The service level is the probability that the amount of inventory on hand during the lead time is sufficient to meet expected demand.
Product at the Jennings Company enjoyed reasonable sales volumes, but its contributions to profit were disappointing. Last year 14,500 units were produced and sold. The selling price is $22.00 per unit, the variable costs is $15.00 per unit, and the ..
If the digital system has a life of ten years and a salvage value of $ 10,000 at that time, what is the IRR of the new system? Should this project be undertaken?
Develop a strategy for a new sport product. In your answer describe the sport product and include, and thoroughly explain, all pertinent steps in developing the strategy.
What is culture shock? What are the four stages of culture shock?
Analyze and evaluate the processing of new application at the CEUPU. Create a process map for new applications - Calculate the time needed to process an individual application cycle time for the process
For legal advice about my liability with respect to the conduct of my agents in another state. I am trying to find information about relevant
Tim Trainer has been asked to come in and help Attorneys at Law Legal administrative assistants with using Word. The administrative assistants must use Word to type up legal briefs using tools they do not use on a normal basis
Suggest short-term recommendations for the set of six jobs at the company
Compute the annual total cost (i.e. the Purchase cost + Ordering cost + Holding cost). (Please read the question more than once)
What is involved in project scope management and why is good project scope management so important on information technology projects.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd