Cost and schedule data for a project that is underway

Assignment Help Operation Management
Reference no: EM13957787

Following are cost and schedule data for a project that is underway.

Using the cost data in the cost table above, create a cumulative cost curve comparing actual versus planned costs

Using the schedule data in the schedule table above, create a Gantt chart comparing actual versus planned schedule performance

Summarize in words what you see project status to be at this time. What do you predict regarding the final cost and final schedule for the project?

Reference no: EM13957787

Questions Cloud

Equilibrium position with a downward velocity : A steel ball weighing 128 pounds (mass= 4 slugs) is suspended from a spring. This stretches the spring 128/485 feet. The ball is started in motion from the equilibrium position with a downward velocity of 9 feet per second.
Internet to read more about the behavioral patterns : Research the South University Online Library and the Internet to read more about the behavioral patterns. Conduct an interview (via phone or face-to-face) of ten or more people in the age group of fifteen to sixty-four years, to survey the impress..
The syllabus outlines the general questions for forum : The syllabus outlines the general questions for forum discussions. In addition to those questions, please address the following question this week:
Differences between manufacturing and service organisations : What are the key differences between manufacturing and service organisations in regards to decisions in “new product and service design” area? Please discuss and give examples.
Cost and schedule data for a project that is underway : Following are cost and schedule data for a project that is underway. Using the cost data in the cost table above, create a cumulative cost curve comparing actual versus planned costs. Using the schedule data in the schedule table above, create a Gant..
What will be the stretch of the spring : A spring (k = 400 N/m) is hung vertically. If a 5 kg mass is attached to the end of the spring and gently lowered to rest position, what will be the stretch of the spring?
Accrediting requirements governing patients treated in unit : You are the director of health information services in a major medical center that maintains both a psychiatric unit and a substance abuse unit in addition to general medical and surgical units. Identify and discuss the confidentiality issues present..
Draw the phase portrait associated : Draw the phase portrait associated with x'' - 2x' + 2x = 0 and draw a rough sketch of the solution x(t) that satisfies x(0) = 1 and x'(0) = 0.
Explain why the required rate of return increased in fiscal : While income has increased in fiscal 2012, is it clear that the company's performance has improved?

Reviews

Write a Review

Operation Management Questions & Answers

  What are three cost-containment measures

What are three cost-containment measures that were implemented through the collective bargaining process in 1985? Why were these considered milestones in curtailing health benefit costs to employees?

  What strategies can you recommend for the project manager

What strategies can you recommend for the project manager who is working in an organization that has not yet been convinced that they need to spend much time defining requirements

  Illustrate what level of safety stock is appropriate if lead

Illustrate what level of safety stock is appropriate if lead time demand is normally distributed with a mean of 80 cases and a standard deviation of 5 cases.

  Small business do to increase its customer retention rate

With a 70 percent customer retention rate (average for most U.S. firms according to the American Management Association), every $1 million of business in 2014 will grow to more than $4 million by 2024. If you retain 80 percent of your customers, the ..

  Explain how channel partners rely on every other to sell

Give an example of every type of channel partner. Explain how channel partners rely on every other to sell their products also services. Give particular examples.

  Examine whether the three approaches can be used

Six Sigma was started at Motorola but gained great visibility as a result of its implementation at General Electric under the tutelage of Jack Welch.

  Intro to cost management system

(Management control systems) Following are activities that are components of a management control system in a production department. For each item listed, discuss whether it is a detector, assessor, effectors, or communications network: Comparing act..

  Indicate approximately how much less the founders

make an estimate of the dilution that Parviz and the founders would have to take in this case if the VCs were to retain their IRR. Indicate approximately how much less the founders would have in their pockets when the company was sold.

  What is the maximum authorized inventory

Lou's Bakery has established that JIT should be used for chocolate chips due to the high probability of the kitchen heat melting the chips. The average demand is 130 cups of chocolate chips per week. How many Kanbans are required for the bakery? What..

  Develop a financial analysis inclusive of short

Develop a financial analysis inclusive of short and long term projections for the New Microsoft XBOX ONE.

  How has your company or the other company which you are

how has your company or another company that you are familiar with used the internet andor related technologies to

  What are key cost advantages of a level production strategy

What are the key cost advantages of a level production strategy over a chase strategy? Of a chase strategy over a level production strategy?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd