General Foundry, Inc., a metal works plant in Milwaukee, has long been trying to avoid the expense of installing air pollution control equipment. The local environment protection group has recently given the foundry 16 weeks to install a complex air filter system on its main smokestack. General Foundry has been warned that it may be forced to close unless the device installed in the allotted period. Lester Harky, the managing partner, wants to make sure that installation of the filtering system progressed smoothly and on time.

General Foundry has identified the following eight activities that need to be performed and their sequential relationship.

Activity

Description

Time (weeks)

Immediate Predecessors

A

Build internal components

2

--

B

Modify roof and floor

4

--

C

Construct collection stack

2

A

D

Pour concrete and install frame

4

A, B

E

Build high-temperature burner

4

C

F

Install pollution control system

3

C

G

Install air pollution device

5

D, E

H

Inspect and test

2

F, G

  1. Construct the appropriate network diagram.
  2. Which jobs can be delayed without delaying the project completion time?
  3. Can General Foundry complete the project on time? Why or why not?
  4. Suppose Lester wants to shorten the completion time and his options are:

Reduce activity D by one week, which costs $700/week;

Reduce activity E by one week, which costs $800/week;

Reduce activity G by one week, which costs $1000/week;

If General Foundry will save $2000 for each week that the earliest completion time is reduced, which single option, if any, should Lester choose?

The following table represents a plan for a project:


Time Estimates (days)

Job No.

Predecessor Job(s)

Optimistic

Most likely

Pessimistic

A

-

1

2

3

B

-

2

3

4

C

A

4

5

6

D

B

8

9

10

E

C, D

2

5

8

F

D

4

5

6

G

E

1

2

3

  1. Construct the appropriate network diagram.
  2. What is the critical path?
  3. What is the expected completion time for the project and what is the variance of project completion time?
  4. Is the probability that the project will take less than 18 days to complete larger than 50% or smaller than 50%?

Reference no: EM133120000

Questions Cloud

Compute annual dollar-weighted rate of return : You purchase a stock for $40 and sell it for $50 after holding it for five years. During this period you collected an annual dividend of $2.
Explain the portfolio management process : Identify five financial instruments used during the COVID period and explain the portfolio management process used to determine whether to invest in any of thes
Discuss the assumptions of the theory : Explain whether Markowitz portfolio theory can be used to create a portfolio with five of the following instruments.
Unable to train to become better communicator : What could be the career fallout for someone who is unwilling or unable to train to become a better communicator?
Construct the appropriate network diagram : General Foundry has identified the following eight activities that need to be performed and their sequential relationship.
How good was your time and defect estimate for various phase : How good was your time and defect estimate for various phases of software development and How good was your program size estimate, i.e., was it close to actual
Compute the expected return on facebook : Compute the Expected Return on Facebook (Meta) Stock (Google search "ticker symbol" for your company to get your company's ticker symbol): you can get the stock
Tremendous amount of largely spontaneous creativity : Do you feel that countries and companies need explicit strategies for technology development, given the tremendous amount of largely spontaneous creativity
New divisor for the index : Consider a price-weighted index comprised of three stocks, which were closed at $20, $40 and $120. Then the third stock announced a 2-for-1 stock split.

Reviews

Write a Review

Finance Basics Questions & Answers

  Financial reporting and analysis

Finance is about Gunns Ltd, a company in dealing with forestry products in Australia. The company has also been listed in Australian Stock Exchange. As many companies producing forestry products, even Gunns Ltd is facing various problems. Due to the ..

  A report on financial accounting

This report is specific for a core understanding for Financial Accounting and its relevant factors.

  Describe the types of financial ratios

Describe the types of financial ratios and other financial performance measures that are used during venture's successful life cycle.

  Differences between sole proprietorship and corporation

Briefly describe the major differences between a sole proprietorship and a corporation

  Prepare a cash budget statement

Calculate the expected value of the apartment in 20 years' time. What is the mortgage loan repayment at the beginning of each month

  What are the implied interest rates

What are the implied interest rates in Europe and the U.S.?

  State pricing theory and no-arbitrage pricing theory

State pricing theory and no-arbitrage pricing theory

  Small business administration

Identify the likely stage for each venture and describe the type of financing each venture is likely to be seeking and identify potential sources for that financing.

  Effect of financial leverage

The Effect of Financial Leverage and working capital management

  Evaluate the basis for the payment to the lender

Evaluate the basis for the payment to the lender and basis for the payment to the company-counterparty.

  Importance of opps, ipps, mpfs and dmepos

Research and discuss the differences and importance of : OPPS, IPPS, MPFS and DMEPOS.

  Time value of money

Time Value of Money project

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd