Construct a network diagram for the project

Assignment Help Operation Management
Reference no: EM13743537

Problem 1

The following data were obtained from a project to create a new portable electronic.

Activity           Duration         Predecessors 

A                     5 Days             ---

B                     6 Days             ---

C                     8 Days             ---

D                     4 Days             A, B

E                      3 Days             C

F                      5 Days             D

G                     5 Days             E, F

H                     9 Days             D

I                       12 Days           G

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

a) What is the Scheduled Completion of the Project?

b) What is the Critical Path of the Project?

c) What is the ES for Activity D?

d) What is the LS for Activity G?

e) What is the EF for Activity B?

f) What is the LF for Activity H?

g) What is the float for Activity I?

Problem 2

The following data were obtained from a project to build a pressure vessel:

Activity           Duration         Predecessors 

A                     6 weeks           ---                               

B                     6 weeks           ---                               

C                     5 weeks           B                                

D                     4 weeks           A, C                           

E                      5 weeks           B                                

F                      7 weeks           D, E, G                       

G                     4 weeks           B

H                     8 weeks           F

I                       5 weeks           G

J                       3 week             I

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions

a) Calculate the scheduled completion time.

b) Identify the critical path

c) What is the slack time (float) for activity A?

d) What is the slack time (float) for activity D?

e) What is the slack time (float) for activity E?

f) What is the slack time (float) for activity G?

Problem 3

The following data were obtained from a project to design a new software package:

Activity           Duration         Predecessors 

A                     5 Days             ---                               

B                     8 Days             ---                               

C                     6 Days             A                                

D                     4 Days             C, B                            

E                      5 Days             A                                

F                      4 Days             D, E, G                                   

G                     4 Days             B, C

H                     3 Day              G

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

a) Calculate the scheduled completion time.

b) Identify the critical path(s)

c) What is the slack time (float) for activity B?

d) What is the slack time (float) for activity D?

e) What is the slack time (float) for activity E?

f) What is the slack time (float) for activity G?

Problem 4

The following data were obtained from an in-house MIS project:

Activity           Duration         Predecessors 

A                     5 Days             ---                               

B                     8 Days             ---                               

C                     5 Days             A                                

D                     4 Days             B

E                      5 Days             B                                

F                      3 Day              C, D               

G                     7 Days             C, D

H                     6 Days             E, F, G

I                       9 Days             E, F

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

a) Calculate the scheduled completion time.

b) Identify the critical path

c) What is the slack time (float) for activity A?

d) What is the slack time (float) for activity D?

e) What is the slack time (float) for activity E?

f) What is the slack time (float) for activity F?

Reference no: EM13743537

Questions Cloud

Explain growth and spread of religious revivalism in muslim : Explain the growth and spread of religious revivalism in Muslim countries since the late 1960s.
Income statement from the information : Create a two-year forecast of the income statement from the information provided in problem number one. Please create three columns of data: current year, year 2, and year 3. Assume that sales increase ten percent per year for year's two and th..
Write a book report of frederick douglas by williams douglas : Write a book report of Frederick Douglas by William's Douglas.
Recent rise of the indian pharmaceutical industry : How might (a) U.S. pharmaceutical companies and (b) U.S. consumers benefit from the rise of the Indian pharmaceutical industry - who might have lost out as a result of the recent rise of the Indian pharmaceutical industry?
Construct a network diagram for the project : The following data were obtained from a project to create a new portable electronic. Construct a network diagram. What is the Scheduled Completion of the Project? for the project.
Review and identify the blood transfusion requirements : Blood transfusion- Review and identify the blood transfusion requirements within that consent form; explain where and how each element is noted within the actual form itself
What were kerma and meroe known for : What were Kerma and Meroe known for?
Discuss how china fared during the fast two decades : Discuss how China fared during the fast two decades of the 20th century Did Yuan Shikai abide by the republican principles advocated by Sun Yat-sen?
Testing for proteins : Testing for Proteins-How did your a priori predictions compare to your actual results in Table 2? If there were any inconsistencies, explain why this occurred

Reviews

Write a Review

Operation Management Questions & Answers

  What are examples of questionable payments in industry

What are examples of questionable payments in industry? If these questionable payments are part of the culture, are they now acceptable behavior for MNCs

  Discusses the decisions of the federal open market committee

You should now find a press release from the Board of Governors of the Federal Reserve System, dated December 16, 2009, which discusses the decisions of the Federal Open Market Committee (FOMC) for that date.

  Explain barriers and enablers in building intrasectoral

Social Entrepreneurial Process: Barriers and Enablers in Building Intrasectoral and Intersectoral Alliances: What factors do you see as enablers and barriers to the three partners (McKinsey, UWNYC, and NYCT) working together effectively? List and ..

  Company to maintain records of such design reviews

exclaimed that there was no need for record keeping as such reviews were considered confidential and it was not in the interest of company to maintain records of such design reviews.

  The capability index formulas to compute the two values

The mean of the production process has shifted to the left of the design limits, You have just used the capability index (Cpk) formulas to compute the two values

  Major air cargo operator or hub

You must prepare a formal 10-12 page research paper on a topic of your choice related to a major air cargo operator or hub

  The concepts of computer modeling

Please select a company that you have feelings about and think about that company in respect to at least one of the concepts that we have talked about in class up till now such as:

  Determine the factors of good management

Determine the factors of good management you would apply to establish this competitive advantage.

  Discuss several advantages of linear programming

Discuss several advantages of linear programming; clearly explain the reasons for your choices. Does anyone know a good Healthcare lawsuit that I can do an essay on.

  Identify major potential legal issues as they pertain

Identify major potential legal issues as they pertain to employees in the U.S. Examine 4-5 legal issues that differ based on employee location (comparing matters in both Europe and Asia to those in the U.S.).

  Describe how organizations can create an ethics culture

Describe how organizations can create an ethics culture

  What were the main benefits apple realized

What IT/IS solution was Apple chosen to address the problem(s) in (a) above?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd