Consider the two auto manufacturing plants

Assignment Help Operation Management
Reference no: EM131229820

Consider the two auto manufacturing plants below:

Plant 1: Number of workstations = 90, TAKT time = 1.5 min

Plant 2: Number of workstations = 60, TAKT time = 2 min

Both plants operate 24 X 7, 365 days a year.  

a. At the end of 1 year, which plant would have made more cars?

b. How much is the annual output of each plant?

c. How much is the flow time in each plant?

d. How much is the WIP inventory in each plant?

Reference no: EM131229820

Questions Cloud

The number of issues regarding trademarks : Internationally, the number of issues regarding trademarks, patents and copyrights continues to grow. The music business is changing rapidly now. Where do you think it will end up as a result of its inability to protect its copyrighted works that are..
The portfolio strategic plan : The portfolio strategic plan is used to meet the organizational strategies and objectives. List five of the key contents required for the strategic plan and explain the responsibilities of the portfolio manager in accomplishing these plans.
Slack time is permitted in critical path activity times : How much “slack time” is permitted in the “critical path” activity times?
Minimum number of female applicants the company should hire : Central Valdosta Manufacturing Corporation had 100 male applicants last year. They hired 60 of them. They also had 50 female applicants of which they hired 20. In order to avoid adverse impact, what is the minimum number of female applicants the comp..
Consider the two auto manufacturing plants : Consider the two auto manufacturing plants below: How much is the annual output of each plant? How much is the flow time in each plant? How much is the WIP inventory in each plant?
How should project risks be monitored and controlled : How should the risks be prioritized? Who should do the prioritization of the project risks? How should project risks be monitored and controlled? Who should develop risk responses and contingency plans? Who should own these responses and plans?
What should be considered when identifying risks : Assume you have just been assigned to a project risk team composed of five members. Your task, as project manager, is to develop a process for handling risks to the project. What methods should be used for identifying risks? Who should be involved in..
Describes critical path and pure project : Which of the following describes a critical path? Which of the following describes a pure project? Which of the following describes the benefit of a functional project?
Independent hotel-caters to both business-leisure travelers : The Evanstonian is an upscale independent hotel that caters to both business and leisure travelers. On average, one-third of the guests checking in each day are liesure travelers. Leisure travelers generally stay for 3.6 nights-twice a long as the av..

Reviews

Write a Review

Operation Management Questions & Answers

  Compensation and benefit systems implemented

Construct a comprehensive research paper on the Compensation and Benefit Systems implemented at a major United States Company. Compensation and Benefit Systems implemented at a major company in the United States.

  Determine the optimal mixture of ingredients

Peoria Packing & Butcher shop produces a sausage mixture in 200 pound batches. The mixture contains three ingredients – chicken, veal and pork. The cost per pound of each of these ingredients is as follows: chicken $3 per pound, veal $8 per pound and..

  What would the average length of the waiting line

The company is considering consolidating its two service desks into one location, staffed by two clerks. The clerks would continue to work at the same individual speed of four minutes per customer. what would the average length of the waiting line (n..

  Calculate measurement error using mse and mad

Calculate a 5-year moving average to forecast the number of mergers for 2012. Use the moving average technique to determine the forecast for 2005 to 2011. Calculate measurement error using MSE and MAD

  Principal distinct component of international logistic

What is principal distinct component of international logistic? What are the elements that differentiate international logistics from domestic logistics? What are the major costs of international logistics?

  What is the utilization of server

Katie Posh runs an upscale nail salon. The service process includes five activities that are conducted in the sequence described below. (The time required for each activity is shown in parentheses): What is the utilization of server 2 (in decimal for..

  What are recent examples of unethical business

What are recent examples of unethical business decisions that have had a large impact on society?

  Airlines operate networks or hub-and-spoke systems

Most large airlines operate networks, or hub-and-spoke systems, which connect many spoke cities (or nodes) with flights to and from a hub airport. How can a network airline profitably serve smaller cities than a low-cost-airline

  Some nonwage issues that might come up in bargaining

What are some nonwage issues that might come up in bargaining? Which ones are the most important and why? Is it easier to compromise on wage or nonwage issues? Why?

  Practices horizontal integration

This week let’s discuss integration. First, name a company the practices horizontal integration. Describe the structure. Now do the same for a company vertically integrated. In your opinion, which is better to work for? Which offers workers the bette..

  Business-level strategies and cost leadership

The Global Automobile industry reviews the state of play in the global automobile industry in 2009, which can easily be expanded through online resources to the current time. The case describes the economics of the industry. Three main Business-level..

  Describe why project management

Explain and describe why project management, as described in the PMBOK, and total quality management are similiar. Do the methodologies used in project management change over time and if so, how and why? List references.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd