Consider project with mean time of completion

Assignment Help Operation Management
Reference no: EM131275760

Consider a project with a mean time of completion of 14.67 days; the variance of the time of completion is 2.83 days. If we need a 99% chance of completion, how many days should we allow? Response Feedback: We need to find y such that P(T < y) = 0.99, where T is a Normal random variable with a mean of 14.67 and a standard deviation of 1.68 So we need to find y such that P( Z < (y-14.67)/1.68 ) = 0.99 However from the tables we know that P(Z < 2.35) is close to 0.99 So (y-14.67)/1.68 must be 2.35, so y must be...

Reference no: EM131275760

Questions Cloud

Requires routine or positive business message : Post your responses to the following statements on the discussion board. If appropriate, include personal experience as part of your answers. Identify and describe a hypothetical scenario for which a routine or positive business message is appropriat..
Better strategy for population health quality of care : Which is the better strategy for population health quality of care - case management or care management? Is Mary Kay an international firm, a multinational, or a transnational firm based on its marketing strategy? find one organization who has union ..
Car rental company is located three miles from the airport : A car rental company is located three miles from the airport. A shuttle bus runs every two minutes on average doing a round trip between the airport and the rental company. The average round trip time is 20 minutes. So the average time for a customer..
Drop in inventory means that the change will be negative : A process has a cycle time of 10 minutes. The throughput time is 9 hours. If the throughput time is reduced to 5 hours without changing the cycle time, what is the change in inventory (as a percentage)? Response Feedback: Throughput rate is 6 units p..
Consider project with mean time of completion : Consider a project with a mean time of completion of 14.67 days; the variance of the time of completion is 2.83 days. If we need a 99% chance of completion, how many days should we allow? Response Feedback: We need to find y such that P(T
Consider project with mean time of completion : Consider a project with a mean time of completion of 14.67 days; the variance of the time of completion is 2.83 days. What is the probability of finishing the project in 17 days? This would be the same as P(Z
Find the average value of the squares : Generate a random number between zero and ten (=RAND()*10) Find its square. Repeat that for one hundred values (copy the line 99 times). Find the average value of the squares.
Supply chain management by its very nature depends : Supply chain management by its very nature depends on relationships and connections. Describe supply chain integration as it applies to relationships and connections. Explain the challenges for integrating business functions and inter-organizational ..

Reviews

Write a Review

Operation Management Questions & Answers

  Discuss the role of information systems in an organization

Discuss the role of information systems in an organization. Compare and contrast various approaches to organizing information system resources. Describe the responsibilities associated with collecting data, designing information systems, and using in..

  Atlantic coast conference basketball tournament

Jeff is an avid UNC-Chapel Hill basketball fan, and drives to the Greensboro Coliseum to watch his beloved Tarheels play in the Atlantic Coast Conference (ACC) basketball tournament. Jeff also surmises that the Blue Devil fan is probably long gone by..

  Determining their intellectual property

Think of two common, current health care firms with which you are familiar. What types of intellectual properties might they own? What factors might they have considered in determining their intellectual property and how it might affect their firm an..

  Describe the two different types of contract formats

Describe the two different types of contract formats used for most solicitations and contracts. Discuss some restrictions that limit the two types.

  How do functional silos prevent process integration

Describe the linkage between supply chain strategies and internal functional strategies and policies. How do functional silos prevent process integration? What are the eight key supply chain business processes, and why are they important when managin..

  Determine risk score and a recommended time frame

It is estimated to cost over $50,000 to replace the machine; however the hazard will be reduced by about 90%, since there is the remote possibility that a new machine might leak. Use the William Fine Method to determine Risk score and a recommend..

  Determine the greatest ethical dilemmas by globalization

Determine the greatest ethical dilemmas created by globalization and the best way to address those dilemmas. Provide specific examples to support your response.

  Vague or generalized submissions will lose significant point

If you were the chair of a nonprofit board, how would you describe the ideal relationship between the board and the CEO from your perspective? Be sure to strengthen your position by using information learned from reading the chapter. Vague or general..

  Assume that the food and drug administration

Assume that the Food and Drug Administration (FDA), using proper procedures, adopts a rule covering future investigations involving the FDA’s regulation of food additives. According to the new rule, the FDA will not regulate food additives without gi..

  Brief summary of the theory and progression in the field

Brief summary of the theory and progression in the field, Study limitations and how these differ across the various study designs

  What dangers are inherent in not evaluating training program

What dangers are inherent in NOT evaluating training programs?

  What is the break-even point in units and revenue

A new piece of equipment will have a fixed cost of $50,000 and the product it would produce has a variable cost of $12.00, and a selling price of $15.00. What is the break-even point in units and revenue? How many units must be sold to make a profit ..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd