Computes the schedule variance performance index

Assignment Help Operation Management
Reference no: EM1373412

Q. A project to build a new bridge seems to be going very well since the project is well ahead of schedule also costs seem to be running very low. A major milestone has been reveryed where the first 2 activities have been totally completed also the third activity is 61 % complete. The planners were only expecting to be 55 % through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected which this would cost $1,421,000 also it was done for only $1,301,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,501,000 however was actually done for $9,001,000. The third also final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,501,000. To date they have spent $5,001,000 on the superstructure.

Computes the schedule variance, schedule performance index also cost performance index for the project to date.

 

 

Reference no: EM1373412

Questions Cloud

Pros and cons of a big highway building program : Assume that you get a summer intern job and a recession start while you are there. Prepare a memo to your boss, who is a member of Congress,
Elucidate what others might be included : Are the factors Gardner selected for evaluation reasonable also complete. Elucidate what others might be included.
Describe how effective was the od consultants data gathering : Describe how effective was the OD consultants' data gathering. The content of the data? The process of describe how the data were collected.
Question about minimum wage : Assume government forced a minimum wage above what otherwise would be equilibrium wage rate for this segment of the labor market.
Computes the schedule variance performance index : This was expected to cost a total of $8,501,000. To date they have spent $5,001,000 on the superstructure. Computes the schedule variance, schedule performance index also cost performance index for the project to date.
Elucidate what are the major internal variables to consider : Elucidate what are the major internal variables to consider in the scanning process. Discuss the levels of internal monitoring which should be conducted. Describe how well you think management conduct environmental assessment.
Describe how does the corporation use its competencies : Describe Shutter fly's business-level strategy. Who is the targeted customer. Which customer needs does the Corporation satisfy. Describe how does the Corporation use its competencies to satisfy these needs.
Determine how ship need from every plant to distribution : The shipping costs per truckload between the plants also distribution centres are given in the table. The Corporation needs to determine how much to ship from every plant to every distribution center also would like to minimize total shipping costs..
Give the gradient operator in paraboloidal coordinates : Given that the le data.txt contains only real numbers seperated by white space, write down a sequence of maple commands that will read the data into a maple list and then plot a histogram of the elements in the list.

Reviews

Write a Review

Operation Management Questions & Answers

  Elucidate what the control chart tells you about the irs

The data for the last week follows: Day # of Non-conformities 1 2 3 4 5 5 10 23 20 15 Construct a 3 standard deviation c chart of non-conformities. Elucidate what the control chart tells you about the IRS telephone operators

  Compute the expected value of every alternative number

Compute the expected value of every alternative number of (dozens of) carnations which could be stocked also select the best decision. Construct the opportunity loss table also determine the best decision.

  Employment agreement

Sandy believes her employer has breached the employment agreement and she should be paid for the two weeks between jobs. Is she right? Explain.

  Sequence of operations in multiple operations

The jobs that consist of multiple operation, what states the sequence in which those operations must be performed?

  Calculate the economic order quantity

How does the Kanban process focus on the individual within the teamwork concept and How is the Kanban process linked to the Kaizen process and What is capacity planning

  Elucidate what is the recommended production rate

Elucidate what is the recommended production rate if a level strategy is adopted with no backorders or stock counts. Elucidate what is the ending inventory for month 4 under this plan.

  Market research explained solution

Let's say your market research firm is hired to assist retail store that is interested in revamping their overall store format in an effort to keep people in their store longer.

  Research mothods on corporate issues

Do you agree that the success of corporations rests in their capability to communicate effectively, to convince stakeholders of their point of view, and persuade them to respond in a desired manner?'

  Two variables and two constraints

Develop your own original Linear Programming problem with the minimum of two variables and two constraints.

  Linear programming-transshipment model

RVW (Restored Volkswagens) buys 15 used VW's at each of two car auctions each week held at different locations. Formulate this problem as a transshipment linear programming model. Solve the problem using the computer. Provide a Excel file.

  Serious financial trouble

Your business, a closely held corporation with 4 other shareholders, is in serious financial trouble. A lender has suggested that it might provide lending if you could reduce your current debt load by 50%.

  Friendly family apple products-linear programming model

On their farm, the Friendly family grows apples that they harvest each fall and make into three products-apple butter, applesauce, and apple jelly. Propose a linear programming model for this problem. Solve the model by using the computer either ex..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd