Compute the price per hour of direct labor

Assignment Help Managerial Accounting
Reference no: EM132418643

Labor rate, including fringe benefits$47per labor hourAnnual labor hours 11,100hoursAnnual materials (parts) purchases$2,110,000 Annual overhead costs:   Materials purchasing, handling, and storage$422,000 Other overhead (depreciation, insurance, taxes, rent)$177,600 Target profit margin (on both labor and materials) 30%

1. Compute the price (rate) per hour of direct labor.

2. Compute the materials markup (in %).

3. What price should the company quote for a job requiring five labor hours and $690 in parts?

Questions To Answer

1. Total labor rate per hour

2. Materials markup

3. Total price quote

Reference no: EM132418643

Questions Cloud

Run a complete variance analysis for cogs : Based on the information given, run a complete variance analysis for COGS by indicating variance conditions for each of the COGS variance components.
Run a complete variance analysis for revenue : Run a complete variance analysis for revenue by indicating variance conditions for each components.
Alternative methods of joint costs allocation : Pacific Lumber processes lumber products for sale to lumber wholesalers. Its most popular line is oak products. Oak tree growers sell Pacific Lumber whole trees
What types of companies use job order costing : What types of companies use job order costing? What types of companies would use process costing?
Compute the price per hour of direct labor : 1. Compute the price (rate) per hour of direct labor. 2. Compute the materials markup (in %).
LUBS5011M - Applied Finance Assignment : LUBS5011M - Applied Finance Assignment Help and Solution, University of Leeds, UK. Calculate simple return for both stocks
What time does simmons arrive home : What time does Simmons arrive home? What is the value-added ratio? Round your percent to one decimal place.
Discuss the barriers in procurement of mega projects : Discuss the barriers in procurement of mega projects globally and particularly in Oman the Critical Success Factors(CSFs) in the procurement process for mega
Report on procurement of mega projects : Construction Procurement Assignment - Report on procurement of mega projects - Critical Success Factors(CSFs) in the procurement process for mega projects

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd