Donna Company would like to estimate the variable and fixed components of its maintenance costs and has compiled the following data for the last five months of operations:
Labor Hours Maintenance Cost
January 190 P677
February 120 P593
March 170 P646
April 110 P623
May 100 P582
Required:
Problem [a] Using the high-low method of analysis, how much is the estimated variable cost per labor hour for maintenance?
Problem [b] Using the high-low method of analysis, how much is the estimated total fixed cost per month?
Problem [c] Using high-low, compute for the expected maintenance cost for June if expected labor hours is 150 hours.
Problem [d] Using the least-squares regression method, how much is the estimated variable cost per labor hour for maintenance?
Problem [e] Using the least-squares regression method, how much is the estimated total fixed cost per month for maintenance?
Problem [f] Using the least-squares regression method, compute for the expected maintenance cost for June if expected labor hours is 150 hours.
Problem [g] Using the least-squares regression equation, where is the total maintenance cost for March located with respect to the regression line?