Planned duration of a project is 28 weeks. Budget at completion for the project is $525,000.

The project is in its 25th week. The actual cost (thus far) is $270,000. At this point in the plan, the planned cost was expected to be $261,000. For the work performed to date, the earned value is estimated at $272,000.

Compute the following for the project:

Cost variance.

Schedule variance.

If rest of the project is assumed to be completed at the current cost performance level, compute estimated total cost at completion of the project.

If rest of the project is assumed to be completed at the current schedule performance level, compute estimated project completion time.

Reference no: EM131276815

Questions Cloud

Shade feasible region-associated objective function value : Identify each constraint (1, 2, 3, 4, 5, and 6) and the objective function line on your graph. Shade the feasible region. What is the optimal solution? What is the associated objective function value?
Is more rapid turnover among employees beneficial to firm : It is generally agreed that the current workers have a very small probability of being employed by the same firm throughout their work lives. In previous generations it was common for people to have just one employer. Is more rapid turnover among emp..
Marketing departments report to the head of sales : Marketing departments report to the head of sales, should be the other way around where the sales department reports to a marketing director?
Workplace enhances employee performance : Why do you think that use of personal devices in the workplace enhances employee performance? How is the work-home balance improved with dual-use-devices? How has IT improved security features of employee dual-use devices?
Compute estimated total cost at completion of the project : Planned duration of a project is 28 weeks. Budget at completion for the project is $525,000. Cost variance. Schedule variance. If rest of the project is assumed to be completed at the current cost performance level, compute estimated total cost at co..
Identify the different segments of the automobile market : Review the important themes within the sub questions of each bullet point. The sub questions are designed to get you thinking about some of the important issues. Identify the different segments of the automobile market. Discuss the types of people wh..
Statements about world population trends : Which of the following statements about world population trends are TRUE: Adam showed Tom that he has a gun then he asked Tom to sign a contract transferring the ownership of Tom’s land to Adam. In this situation
Ethics is a hot topic in business : Ethics is a hot topic in business, as well as in Project Management. Read the PDF entitled "Ethics in Project Management". Using some of the examples presented therein, what kinds of dilemmas have you either seen, encountered, or can envision from yo..
Analyze the use of an enterprise software systems : Analyze the use of an Enterprise Software Systems (ESS) in a health care organization with regard to its effects on operational outcomes.  Based on the recommendations that you made in the Part I of this discussion, determine a significant drawback o..

Reviews

Write a Review

Operation Management Questions & Answers

  Major ethical considerations that face the project manager

Identify and characterize some major ethical considerations that face the project manager. Identify one important ethical issue facing a project manager, and analyze it in detail. If possible, provide examples, cases, and data as well as sources.

  Identify problem caused by goal misalignment

Goal Alignment in Your Company Are your incentives aligned with the goals of your company? If not, identify a problem caused by goal misalignment. Suggest a change that would address the problem. Compute the profit consequences of the change.

  An air conditioning repair department manager has compiled

An air conditioning repair department manager has compiled data on the primary reason for 41 service calls for the previous week, as shown in the table. Using the data, make a check sheet for the problem types for each customer type, and then cons..

  Describe corporate strategic alliance

Describe corporate strategic alliance and discuss why a company would want to develop one. Are strategic alliances necessary for a company to expand internationally

  Make these future investments

At the end of Year 2, Spring Corp. invests $4,000, at the end of Year 4, it invests $7,000, and at the end of Year 8, $7,500. Determine the amount of money that the company would have to have now to make these future investments if it can typically e..

  In international businesses discuss ethical challenges faced

In international businesses discuss ethical challenges faced in developing products. Research Scripture and support your decision with an appropriate Biblical example. Give an example from your own experience of an effective push strategy and an effe..

  Examine how you can improve your current communication

most of us have situations in which we find it difficult to communicate. improving your written communication skills

  What is ethical and unethical

What is ethical and unethical when the company design a printers and the ink catridges will work only if made in the same region. i.g. ink catridges from U.S. will not work in Asia.This will prevent consumers from buying the product at a lower price ..

  Over what range of call minutes will each plan be optimal

determine the total charge under each plan for this case: 120 minutes of days calls and 40 minutes of evening calls in a week.

  Develop a schedule for a project

What types of information can we learn about the project by reviewing the project schedule and all the information used to generate it?

  Exponential smoothing for seasonal model without trend

Killian Corporation makes hot chocolate mix. Sales, in thousands of pounds, follow a seasonal pattern. Quarterly forecasts are made using exponential smoothing for a seasonal model without trend. Currently S4 = 186.5, c1 = 1.4, c2 = 0.6, c3 = 0.3, an..

  What are costs and benefits of organizational structure

Think about a company where the product necessitates input from employees at all levels.Each employee is a specialist with special knowledge that must be shared throughout the organization. What are the costs and benefits of an organizational structu..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd