Adventure company manufactures camping tents from a lightweight sythinetic fabric. Each tent has a standard materials cost of $42, consisting of 4 yards of fabric at $10.50 per yard. The standards call for 2 hours of assembly at $20 per hour.
The following data were recorded for October, the first month of operations:
fabric purchased 9,000 yards x $10.00 per yard
fabrics used in production of 1,700 tents 7,000 yards
direct labor used 3,600 hours x $21.50 per hour
Required
Question a. Compute all standard cost variances for materials and labor
Question b. Give one possible reason for each of the preceding variances.
Question c. Determine the standard variable cost of the 1,700 tents produced, separated into direct materials and labor.