Three years ago the Sharp Printing (SP) strategic management group set a goal of having a color laser printer available for the consumer and small business market for less than $200. A few months later the senior management met off-site to discuss the new product. The results of this meeting were a set of general technical specifications along with major deliverables, a product launch date, and a cost estimate based on prior experience.
Shortly afterward, a meeting was arranged for middle management explaining the project goals, major responsibilities, the project start date, and importance of meeting the product launch date within the cost estimate. Members of all departments involved attended the meeting. Excitement was high. Although everyone saw the risks as high, the promised rewards for the company and the personnel were emblazoned in their minds. A few participants questioned the legitimacy of the project duration and cost estimates. A couple of R&D people were worried about the technology required to produce the high-quality product for less than $200. But given the excitement of the moment, everyone agreed the project was worth doing and doable. The color laser printer project was to have the highest project priority in the company.
Lauren was selected to be the project manager. She had 15 years of experience in printer design and manufacture, which included successful management of several projects related to printers for commercial markets. Since she was one of those uncomfortable with the project cost and time estimates, she felt getting good bottom-up time and cost estimates for the deliverables was her first concern. She quickly had a meeting with the significant stakeholders to create a WBS identifying the work packages and organizational unit responsible for implementing the work packages. Lauren stressed she wanted time and cost estimates from those who would do the work or were the most knowledgeable, if possible. Getting estimates from more than one source was encouraged. Estimates were due in two weeks.
The compiled estimates were placed in the WBS/OBS. The corresponding cost estimate seemed to be in error. The cost estimate was $1,250,000 over the senior management estimate; this represents about a 20 percent overrun! The time estimate from the developed project network was only four months over the top management time estimate. Another meeting was scheduled with the significant stakeholders to check the estimates and to brainstorm for alternative solutions; the cost and time estimates appeared to be reasonable. Some of the suggestions for the brainstorming session are listed below.
- Change scope.
- Outsource technology design.
- Use the priority matrix (found in Chapter 4) to get top management to clarify their priorities.
- Partner with another organization or build a research consortium to share costs and to share the newly developed technology and production methods.
- Cancel the project.
- Commission a break-even study for the laser printer.
Very little in the way of concrete savings was identified, although there was consensus that time could be compressed to the market launch date, but at additional costs.
Lauren met with the marketing (Connor), production (Kim), and design (Gage) managers who yielded some ideas for cutting costs, but nothing significant enough to have a large impact. Gage remarked, â€Å"I wouldn't want to be the one to deliver the message to top management that their cost estimate is $1,250,000 off! Good luck, Lauren.

Q1. At this point, what would you do if you were the project manager?

Q2. Was top management acting correctly in developing an estimate?

Q3. What estimating techniques should be used for a mission critical project such as this?

Reference no: EM13108929

Questions Cloud

Determine how manufacturer maximize revenue : A furniture manufacturer produces tables and chairs. Each table and chair must be made entirely out of oak or entirely out of pine. A total of 150 board feet of oak and 210 board feet of pine are available.
Illustrate what are the ethical implications of individual : Illustrate what is the role of leadership in creating, managing and sustaining innovation? Illustrate what are the ethical implications of an individual reward system? Support your answer.
Calculate the heat of neutralization : Calculate the heat of neutralization when it is given that : heat capacity of the calorimeter =28.7 J/oC ,the specific heat of the mixture =4.184 J/goC, density of the solution =1.02 g/mL.
Illustrate what dimension of real estate body of knowledge : Issues relating to real estate deeds, leases and contracts are best categorized into illustrate what dimension of the real estate body of knowledge?
Case study - sharp printing : Three years ago the Sharp Printing (SP) strategic management group set a goal of having a color laser printer available for the consumer and small business market for less than $200.
Self-reported-measured male heights : As part of the National Health and Nutrition Examination Survey, the Department of Health and Human Services obtained self-reported heights and measured heights for males aged 12-16. All measurement is in inches. Listed below are sample results.
Chemical reaction at constant temperature and pressure : Determine the values of q, w, and ΔE0rxn for this given chemical reaction at constant temperature and pressure?
Explain why is it difficult for an industry in one strategic : suggest the questions that the computer might raise if it detected the subsequent pattern: Inventory-carrying cost and inventory stock availability are dropping.
Determine sample size suggested by statement : More than 5 percentage points in either direction from what would have been got by interviewing all voters in United States." Determine sample size suggested by this statement.

Reviews

Write a Review

Operation Management Questions & Answers

  Six sigma dmaic improvement approach

Identify an organization that uses the Six Sigma DMAIC improvement approach. Describe in a short paper some of the ways that this organization has applied DMAIC and the results it has achieved.

  Staffing procedures for measurement

Part of a strategic staffing plan includes staffing procedures for measurement that support reporting requirements and the resource needs of the organization.

  What are the total costs of delivery for style

What are the total costs of delivering Style A hats to the port of importation? What are the total costs of delivery for Style B hats to the port of importation

  Managing supply chain and logistics

Imagine you are a marketing consultant brought in to help a company who has a product that is so successful they cannot keep up with customer demand.

  Calculate potential direct and indirect costs

Amanda and Chris McDermott own a small business, Plastic Dollars, which produces and maintains stored value cards for retailers. Most of the cards they sell are gift cards, such as those available in various restaurants and stores.

  Complexity of the information system structure

Identify and discuss factors that can increase the size and complexity of the information system structure (beyond those discussed in the text).

  How changes in environment affect success of company

Why does each generic business model require a difficult set of business-level strategies? How do changes in the environment affect the success of a company's business model?

  What would his total ordering cost be for the year

There are 360 working days per year and the lead-time is 5 days. If Mark orders 200 units each time he places an order, what would his total ordering cost be for the year?

  When harry told brian he was building the new room

When Harry told Brian he was building the new room, Brian just smiled. Brian also heard that Harry borrowed money from his aunt to buy the trains.

  Illustrate what you have learned in this course

illustrate what you have learned in this course or your future progress/improvement. State whether you achieved the course objectives.

  A chemical firm produces sodium

A chemical firm produces sodium n 100-pounds bags. Demand for this product is 25 tons per day. The capacity to produce the product is 75 tons per day

  Calculating mean absolute deviation

Since May of 2005, the purchase manager at a department store has been using a 4-period moving average to forecast sales in upcoming months.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd