a. Develop a project network for this problem.
b- Determine the critical path for the campaign project and the expected project completion time. (Use the expected time for the activity completion time)
c- Determine the probability that the project will be completed in less than 34 days.
d- Determine the probability that the project will take more than 29 days
A manager just received a new price list from a supplier. It will now cost $1.00 a box for order quantities of 801 or more boxes, $1.10 a box for 200 to 800 boxes, and $1.20 a box for smaller quantities. Ordering cost is $80 per order and carrying co..
Would a U.S. MNC doing business in Germany find it easier to introduce these concepts into German operations, or would there be more receptivity to them back in the United States? Why? What if the U.S. multinational were introducing these ideas in..
Use an appropriate technique to develop a forecast for the expected number three weeks Can someone please show me how to work this problem?
Describe the circumstances that would position a domestic firm to engage in international business. Are there any factors that are particularly relevant as compared to others? Also, explain why a large, profitable domestic firm might chose not to ..
Bob's annual fixed costs for space, equipment, and supplies is $61,000. Which is the preferred process for Bob and why?
Discuss the basic design dimensions managers must consider in structuring an organization. Describe five structural configurations for organizations.
Devise an explanation as to how the Blue Cross health plan can fall under the definition of "hospital and medical service corporation."
rush franken receives about 60000 calls in a 3 hour period into his phone lines for his radio show but he is only able
Following the Activity On Node system conduct a grocery store run. Use circles with numbers and list what each step is. Add times, total process time, and identify the bottleneck.
Machine's output is known to be approximately Normal with mean of 2.0 litter and standard deviation of 0.01 litter. Output is monitored using means of samples of 5observations. Determine upper and lower control limits that will include roughly 95...
Describe three characteristics of online web conference meetings that distinguish them from other conference meetings.
Individual contributors not being used to being a team player. What about the other way around? Is there any thought about how people that are used to working in a team based environment make the successful switch to an individual contributor role?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd