Three activities are candidates for crashing on a project network for a large computer installation (all of course are critical). Activity details are in the following table:

Normal Crash Normal Total Cost Immediate
Activity Time(Days) Time(Days) Cost W/ Crashing Predecessor(s)
A 7 6 $4,500 $5,000 ______
B 4 2 $1,400 $3,100 A
C 11 9 $4,600 $6,800 B

1)Activity that should be crashed first to reducethe project duration by 1 day is __A???_____.

2)Activity that should be crashed next to reduce the project duration by one additional day is __B???________.

3)Total cost of crashing the project by 2 days =$_____________.

 

Reference no: EM13104176

Questions Cloud

Finding the crossover point : A product is currently made in a process-focused shop, where fixed costs are $9000 per year and variable cost is $50 per unit. The firm is considering a fundamental shift in process, to repetitive manufacture.
Characteristics of team affect to make ineffective decisions : Why is this group a team? Write down characteristics of team predispose it to making ineffective decisions? Write down the characteristics of group-think which are manifested in worm team?
Number of hours between break-downs for machines : Given the following number of hours between breakdowns for 4 machines, are the machines significantly different? If so, how are they different? Which machine is the best? Which machine is the worst?
What would their separation distance : Suppose the charge of one is increased by twenty seven times while the charge of the other is reduced to one-third its initial value. What would their separation distance have to be changed to in order to keep the force between them the same?
Calculating total cost of crashing the project : Three activities are candidates for crashing on a project network for a large computer installation (all of course are critical).
Compute the standard deviation : An instructor allows students to take an exam as many times as needed until the student obtains a passing grade. The following is a record of the number of students in a class of 20 who took the test and the number of tests taken in order to obtain a..
Estimate the total crashing cost : The following is a table of activities associated with a project at Bill Figg Enterprises, their durations and what activities each must precede and the crash cost to reduce duration per week.
Roles of patients-caregivers influence health communications : Patients and caregivers may conform to the specific role during health care visit. This generally occurs as cultural background or upbringing of either patient or caregiver.
Creating production constraints for work area : A manufacturer makes two products, windows and doors. Each must be processed through two work areas. Work are #1 has 48 hours of available production time.

Reviews

Write a Review

Operation Management Questions & Answers

  A marketing research group needs to contact wives

For a telephone survey, a marketing research group needs to contact at least 150 wives, 120 husbands, 100 single adult males, and 110 single adult females

  The annual holding cost is the purchasing price

The coffeehouse estimates that it costs $45 in paperwork and labor to place an order for the coffee, and the annual holding cost is 15% of the purchasing price.

  Explain regional economic integration

The European Union is an example of a regional economic integration.

  Assume now that carwash had been using the regression

assume now that CarWash had been using the regression model in forecasting. What would you conclude about its performance? Show details for updated MAD calculations

  Prefabricated buildings manufacturer and your first job

You are hired by a prefabricated buildings manufacturer and your first job is to calculate the cost of 100 prefabricated structures. Each structure has 1,000 square feet of floor space and 8 foot ceilings.

  Illustrate what is the solution for the new lp

Supposed the objective function is changed to, do you need to re-graph the feasible region of this LP. Why. Illustrate what is the solution for the new LP.

  How would you characterize best buy''s competitive strategy

How would you characterize Best Buy's competitive strategy? Should it be classified as a low-cost provider strategy? A differentiation strategy?

  Explain the economic production

The economic production quantity is 500 units (units are delivered to the user department as they come off the production line). If the firm decides to buy this item from an outside supplier rather than producing it, the economic purchase quantity..

  Which forecasting technique would you consider

From the choice of simple moving average, weighted moving average, exponential smoothing, and linear regression analysis, which forecasting technique would you consider the most accurate? Why?

  Explain how hrm system is implemented in this hotel

Illustrate what is the percentage change in Sun Path's total productivity measure between 2011 & 2012. Explain how HRM system is implemented in this hotel.

  How do we remain objective in evaluating employee

How do we remain objective in evaluating employee performance? How do we objectively evaluate subjective skills such as communication and performance?

  Ow many dozen cookies should you make with each batch

The same bakery also makes gourmet chocolate-chip cookies by the dozen to sell to local grocers. The bakery is contracted to supply 30 dozen cookies a day to the grocers.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd