Reference no: EM1378043 
                                                                               
                                       
Question1. A sales project at month five had an actual cost of $34,000, a planned expense of $42,000, and a value completed of $39,000. Determine the cost and schedule variance and CPI and SPI.
Question2. A project to develop a county park has an actual cost in month 17 of $350,000, a planned cost of $475,000, and a value completed of $300,000. Find the cost and schedule variances and the three indexes.
Question3. A project to develop technology training seminars is 5 days behind schedule at day 65. It had a planned cost of $735,000 for this point in time, but the actual cost is only $550,000. Estimate the schedule and cost variances. Re-estimate the variances if the actual cost had been $750,000.
Question4. For the following test marketing project at week 6, calculate the cost, schedule, and time variances. Also, calculate the CPI, SPI, CSI,, and the ETC and EAC.
Activity Predecessors Duration WKs	 Budget $	Act Cost$ % completed
a	 --	 2	 300	 400	 100
b	 --	 3	 200	 180	 100
c	 a	 2	 250	 300	 100
d	 a	 5	 600	 400	 20
e	 b,c	 4	 400	 200	 20
 
                                       
                                     
                                    
	
		| Discuss the effect of any seasonal factors utilizing
                                        : discuss the confidence intervals also their usefulness based on the number of data points. Discuss the effect of any seasonal factors utilizing the process  performance data collected each week. | 
		| Critical safety or security challenges
                                        : Assume if there were critical safety or security challenges confronting a zoo environment; what steps would a manager take to overcome them? | 
		| Indicates that at least two of the projects must be done
                                        : it takes two hours to refill the container also return it to the bathtub. Illustrate what happens to the system over time. | 
		| Explore corporate websites that have a recruitment area
                                        : Explore 4 to 6 corporate websites that have a recruitment area as well  as note their major features and strengths and weaknesses. Create a  table that contains | 
		| Calculating the cpi, spi and csi
                                        : A sales project at month five had an actual cost of $34,000, a planned expense of $42,000, and a value completed of $39,000. Determine the cost and schedule variance and CPI and SPI. | 
		| Explain your typical customer''s needs
                                        : How has the doubling of your firm's customer base every 6 months  affected its ability to maintain this focus on the customer? If this  dramatic growth continues, what are some specific actions your firm will  take to retain its goal of "focus on the.. | 
		| Should the organization sell the lease or drill
                                        : Four possible outcomes are listed below,  together with probabilities also payouts. Should the organization sell  the lease or drill. When preparing a claim that is optically scanned, births dates are keyed in with explain how many digits. | 
		| Evaluate marginal tax rate
                                        : Suppose her marginal tax rate is 40 % this year and next year, and that  she can earn an after-tax rate of return of 8% on her investments. | 
		| How does victoria''s secret utilize enhancement
                                        : How does Victoria's Secret utilize enhancement of the self to attract  consumers? Would you imagine males to visit the site as well as females? |