PART A: Discrete Event Simulation model

Description of the port operation (simplified)

As you can imagine, operations at a port container are extremely complex, but for the sake of simplicity in this project, only some important features will be considered here.

The main steps in the operation of the terminal are the following:

- Once a vessel arrives to the port, it has to wait for an empty berth AND a tug to be available before it can be moved to the unloading area.
- When the vessel reaches the berth, it has to wait until there are cranes AND a gang available to unload it.
- As soon as the number of cranes required (as explained below) and the gang to operate them are available, the vessel is unloaded.
- The next step is loading the vessel. As for the unloading, this activity requires one or more cranes (more on this below) and a gang.
- Upon finishing the loading, the vessel will not leave the berth until a tug is available to pull it out of the port.

Resources

For the container port being analysed, there are four different resources:
- Berths - this terminal consists of 13 berthing points
- Cranes - there are at present 23 cranes
- Tug boats - there are at the moment 2 tug boats
- Gangs - these are sets of usually 10 - 15 workers with different skills but for the simulation project you can consider a gang as a unit and do not need to be concerned by the number of workers forming a gang. The number of gangs available depend on whether it is a day shift or a night shift and this is discussed in detail in the following section.

What is required of you:

1. Start with an Activity Cycle Diagram as management wants to be sure your interpretation of the problem is correct. If needed, don't hesitate to ask management (aka "Alicia").

2. Develop an initial model for scenario 1, where vessels are allocated the first berth that is available.

3. Calculate parameters such as:
- total time from arrival to the port to departure for the ship.
- time waiting for a berth, time waiting for a gang and a tug.
- time waiting for a crane.
- Utilisation of berths, tugs, cranes.
- Identification of bottlenecks (if any) and in this case, you should suggest a possible solution.
- Comment on the utilisation of the expensive resources (as mentioned above).

4. Develop a second model for scenario 2 where 8 berths are allocated to feeders only and 5 berths to mother-type vessels. Calculate similar parameters to those you estimated for scenario 1. Comment on your results and compare both scenarios.

PART B:

Operating a container terminal efficiently is difficult as shown in the many studies of this area. The main problem is that the obtaining the "balance between the shipowners who request quick service of their ships and economical use of allocated resources is not easy. Since both container ships and container port facilities are very expensive, it is desirable to utilize them as intensively as possible."(Dragovic, 2007)

Let's assume a fixed number of ships arriving per month as the variability of arrivals per month is not an important factor in this analysis. This is shown in Table 1:

Month

Ships Arriving

 

Month

Ships Arriving

Jan

249

 

July

222

Feb

237

 

Aug

272

Mar

260

 

Sep

266

Apr

258

 

Oct

264

May

268

 

Nov

233

1,June

239

 

Dec

222

Of these 40% are feeders while 60% are mothers. The analysis of the costs requires some information on the number of containers carried in these vessels. Containers are usually 20 ft (6.1 metres) long. Although containers vary in height, the most common height for ship containers is 2.59 metres. This container is called TEU. Then the capacity of the vessel or the container terminal is measured in units of TEU's.

For our project, it has been established that feeders have a capacity between 1,000 and 2,000 TEU's with the most likely value being 1,420. For mothers the capacity is in the range 3,001 to 5,200 with the most likely value being 4,200.

Another important factor regarding costs is the time taken to unload/load the vessel. We know the time taken by a crane to unload a container and this is 0.072 hours (independent of the type of vessel). Therefore, the time to unload/load a vessel will depend on the number of cranes used. From part A we know that mother-type vessels, being larger, require between 3 and 5 cranes to be unloaded (you can assume equal probability of requiring 3, 4 or 5 cranes). On the other hand, feeder-type vessels require only between 1 and 3 cranes for their operation.Given this information you should be able to work out the time to unload/load a vessel. Assume for this part of the exercise that the number of cranes used to unload is the same as the number of cranes needed to later load the vessel. The cost of using a crane per hour is given by $38.80.

There is also the cost per hour of having a ship in port. This is given by $1,161. See NOTE 3 below.

As mentioned previously, there can be delays due, for example, to having to berth the vessel far from where the containers that will be loaded into it are stored. The cost of waiting per container per hour (or fraction) is $1.40. We know the proportion of vessels that are delayed and this is shown in Table 2:

Hours

Percentage Delay

On time

50.00%

0-1

25.00%

1-2

20.00%

2-3

5.00%

This table applies equally to mother and feeder vessels.

a. You need to calculate the total cost of operation of the terminal. We will ignore fixed costs since they are not affected by the number of vessels visiting the terminal. Comment on which variables are most important.

b. It's also known that when more personnel is hired at an annual cost of $50,000 per gang there is a 10% reduction in the number of hours (or fraction) the vessel is delayed. This means that if for example, at the moment and for a given month there are (on average) 15.6 vessels waiting between 1-2 hours and 2.6 vessels waiting between 2 and 3 hours and one gang is added, then the number of vessels that will wait between 2-3 hours will be reduced by 10%. This 10% will now wait between 1 and 2 hours. This means that 2.34 (= 2.6 x 0.90) vessels on average wait between 2 and 3 and (2.6 x 0.10) + 15.6 x 0.90 = 14.3 will wait between 1 and 2 hours. Management (aka "Alicia") would like to know if the addition of more gangs would decrease the total cost. Modify your model to incorporate the addition of one, two or three more gangs and comment on your findings.

For the cost analysis, we are told that the cost of having a vessel in the port is $1,161 per hour. We are not given any more information on how long the vessel is in the port but you can make the following two approximations:

a. The time taken to load the vessel will be 15% longer than the time it takes to unload the vessel. Notice as well that the time to unload a vessel is a function of the number of cranes used and the number of containers. You are told that the time taken to unload a container per crane is 0.072 hours. You can assume the time is a linear function of the number of cranes used, which means that if you have one container and one crane, it will take 0.072 hours to unload this container, but if you have two cranes then it will take 0.072 (hours)/2 (cranes) = 0.036 hours to unload the container. Considering this, you can calculate the time taken to unload the vessel and the time that it takes to load it will be 15% larger.

b. Note as well that there is a delay that can be calculated from the delay table (think of a discrete distribution to obtain this time). This delay will be added to the time taken to unload and then to load the vessel and this will give you the total time the ship is in port.

c. Notice that as far as this part of the model you can ignore the time taken by the tug to pull the vessel in and out of the quay.

Attachment:- Final project 2015-2016.rar

Reference no: EM131205822

Questions Cloud

What is the role of the project client sponsor or customer : Is project control different in an Agile project? What is the role of a project manager in controlling an Agile project? What is the role of the project client, sponsor, or customer at controlling project changes?
Calculate the stripper well selling price : Calculate the stripper well selling price thatwill make the economics of selling at year 0 a break-even withabandonment at year 0.
Consider technology and how it influences decision making : Discuss how technologies or information systems have contributed to the problem. Discuss how you will propose technology be implemented into the solution.
Find the components of cash flow from assets : What was the change in net working capital during 2015 for Dawg Town, Inc? Hint: You will have to use the cash flow identity to find the components of cash flow from assets?
Calculate the total cost of operation of the terminal : MG308- Simulation Modelling and Analysis - Start with an Activity Cycle Diagram as management wants to be sure your interpretation of the problem is correct. If needed, don't hesitate to ask management and calculate the total cost of operation of t..
Why supply chain management is important to regal and firms : Can you practice the types of supply chain management without the ethical relationships in the supply chain? What do you think is the MOST important reason why supply chain management is important to Regal and firms like it? Why?
Determine the norton equivalent circuit from the results : Determine the Norton equivalent circuit from the results. The Norton current can be determined from the maximum power level.
Calculate the value of cash and marketable securities : Calculate the value of cash and marketable securities. (Use 365 days a year. Round your intermediate calculations and final answer to the nearest dollar amount.)
How would you respond to your partner : Your partner tells you that his wife is sick and he could really use that marijuana at home for medicinal purposes to help her with her pain. How would you respond to your partner?

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd