A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 63% complete. The planners were only expecting to be 52% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,422,000 and it was done for only $1,302,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,502,000 but was actually done for $9,002,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,502,000. To date they have spent $5,002,000 on the superstructure.

Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)

Reference no: EM1390902

Questions Cloud

What is the standard error of the mean : A random sample of 100 computers showed a mean of 115 gigabytes used with a standard deviation of 20 gigabytes. What is the standard error of the mean.
Select a public organization of your choice and run a pests : Select a public organization of your choice and run a PESTS analysis. Based on your analysis, illustrate what strategic initiative would you recommend
Illustrate what is your estimate of the stock price : Additionally, the consultant believes which the required return used by Ragan, Inc. is too high and which the average required return rate is more appropriate. Under this growth rate assumption, illustrate what is your estimate of the stock price?
Forces that cause the change in filtration rate : Determine the forces that cause the change in filtration rate as plasma passes through the capillary?
Calculate the schedule variance schedule performance index : Calculate the schedule variance, schedule performance index,and cost performance index for the project to date
P-value to the confidence interval for the mean : Suppose that you do a test for H0: μ = 6 against HA: μ &neq; 6 you obtain a sample mean of 6.5 and the test gives you a a p-value of 6%. We want to connect the p-value to the confidence interval for the mean.
Identify key gaps in planning for the exit : Identify key gaps in planning for the exit. Provide recommendations on the exit strategy. Is the sale the right one? What steps ought to be taken to maximize the sales-price?
Cxplain the variation within a species : Claussen and colleagues proposed two hypotheses to describe this variation within a species. There are genetic differences between populations of plants found at different elevations.
Probability that an executive who speaks a foreign language : What is the probability that an executive who speaks a foreign language has not traveled internationally?

Reviews

Write a Review

 

Operation Management Questions & Answers

  Analyze the information on traditional training methods

review and analyze the information on traditional training methods. Which do you think tend to be the most effective and why?

  Discounts are very commonly offered in this business

The prospective buyer says, "I would buy your line of cleaning products if you offered a quantity discount." The salesperson responded, "Discounts are very commonly offered in this business and if you will order today

  What can they learn from the adopting innovation

Recommend how an industry leader should search, select, implement, acquire, execute, launch, and sustain an innovative offering that is appropriate for the chosen industry. What can they learn from the adopting innovation?

  Illustrate what is the process cycle time

Illustrate what is the process cycle time. If the firm operates 10 hours per day, 5 days per week, illustrate what is the weekly capacity of this work cell.

  The sum of ordering and holding boxes of staples

A car rental agency uses 96 boxes of staples a year. The boxes cost $4 each. It costs $10 to order staples, and carrying costs are $0.80 per box on an annual basis

  For five years, baby-food makers baby-one corporation

For five years, baby-food makers Baby-One Corporation and Baby-B-Mine, Inc., bith use the phrase "Tastes Good" on their labels. Baby-One files suit against Baby-B-Mine

  Illustrate what would occur if jason was a consumer

If Jason fails to pay both Joanna also Berkeley also y forecloses their security interests, who has priority on cash register. Illustrate what would occur if Jason was a consumer who purchased goods for personal use.

  How can you determine if implementation has been successful

Which installation options are available for the Customer Tracking System? Which would you recommend?

  Transnational solution suggests that technical and marketing

Organizing for Worldwide Effectiveness: the Transnational Solution" suggests that technical and marketing functions be integrated within each subsidiary of any organization. What are the strengths of such an organization? What are the weaknesses o..

  Elucidate what would you have to do to the costs to assure

The supply also demand for economy cars also the total cost of moving these vehicles between sites are shown below. Elucidate what would you have to do to the costs to assure which A always sends a car to D as part of the optimal solution.

  How much safety inventory does the store carry

How much safety inventory does the store carry? what service level does Sam's club achive as a result of this policy?

  Concept of value of a loyal customer

Joe, the owner manager of Joe's Barbeque, has recently become acquainted with the concept of Value of a Loyal Customer (VLC). He had always rather intuitively thought that his "regulars" were the ones that were most valuable to his business.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd