Your project to obtain charitable donations is now 30 days into a planned 40-day project. The project is divided into three activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 25 days of the project and to bring in $25,000. Even though we are 30 days into the project we still see that we have only 90% of this activity complete. The second activity relates to company donations and is scheduled to run for 30 days starting on day 5 and extending through day 35.We estimate that even though we should have (25/30) 83% of this activity complete, it is actually only 50% complete. This part of the project was scheduled to bring in $150,000 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $50,000. So far $175,000 has actually been brought in on the project.
Calculate the schedule variance, schedule performance index, and cost (actually value in this case) performance index. How is the project going? Hint: Note that this problem is different since revenue rather than cost is the relevant measure. Use care in how the measures are interpreted.
1) What is job evaluation? What method(s) of job position evaluation does employer use? Explain why. (Remember, "Job Evaluation" is not the same as "Performance Evaluation.")
How are leadership traits and ethics addressed in the business world today?
What type of strategy will you use to meet this demand? What impact will this strategy have on the production line? What are some of the advantages and disadvantages of making this shift?
The forecasted demand for fudge for the next four months is 140,160,90 and 70 pounds. A) What is the recommended production rate if a level strategy is adopted with no back orders or stockouts
Computer upgrades have a nominal time of 80 minutes. Samples of five observations each have been taken, and the results are as listed.
Why are media schedules needed? What goal(s) are being attained? Why would it be wise to use different advertising methods? Explain.
Hottenstein, Giffith, and Hult, attorneys at law, do a great deal of printing. The firm uses a single type of printer with annual demand for print cartridges of 480 per year.
At its largest manufacturing facility, in Jakarta, the company produces subcomponents at a rate of 300 per day, and it uses these subcomponets at a rate of 12,500 per year (of 250 working days). Holding costs are $2 per item per year, and ordering..
How many gallons of raw material should they purchase and what is the probability that they will run out of raw material?
You will develop a report that includes the costs, agenda (with the specific training that will be done), training, supplies, and whatever else can achieve the goal of becoming an effective team. The report can be in any format you deem necessary..
Elucidate what is the optimal solution. describe how many workers should be assigned to every type of machine. Every product needs the subsequent processing times (in hours) on every of 3 machines.
Use the internet to research how an interviewee or a current employee might negotiate better pay and/or benefits. Consider using a search term like "negotiating pay and benefits" or "how to negotiate with your boss."
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd