Calculate the percentage idle time for the line

Assignment Help Operation Management
Reference no: EM13109706

Task Task Time(seconds) Immediate
Predecessor
A 45 -
B 11 A
C 9 B
D 50 -
E 26 D
F 11 E
G 12 C
H 10 C
I 9 F, G, H
J 10 I
 
 
  193  
 

 
 

Balance the line using the largest positional weight heuristic. Break ties with the most following tasks heuristic. Use a cycle time of 50 seconds.

Work stations Following Tasks

I

II

III

IV

V

Calculate the percentage idle time for the line. (Round your answer to 1 decimal place. Omit the "%" sign in your response.)