The estimated times and immediate predecessors for the activities in a project at George Kyparis's retinal scanning company are given in the following table. Assume that the activity times are independent.
ACTIVITY
IMMEDIATE PREDECESSOR
TIME (WEEKS)
a
m
b
A
-
9
10
11
B
4
16
C
D
5
8
a) Calculate the expected time and variance for each activity.
b) What is the expected completion time of the critical path? What is the expected completion time of the other path in the network?
c) What is the variance of the critical path? What is the variance of the other path in the network?
d) If the time to complete path A-C is normally distributed, what is the probability that this path will be finished in 22 weeks or less?
e) If the time to complete path B-D is normally distributed, what is the probability that this path will be finished in 22 weeks or less?
f) Explain why the probability that the critical path will be finished in 22 weeks or less is not necessarily the probability that the project will be finished in 22 weeks or less.
Evaluate the efficiency and effectiveness of the process selected in Week Two using the data collected. Determine areas for improvement
Consider the different means of differentiating products and services. Which ones do you believe have the MOST impact on a consumer's choices and WHY? Can you think of certain BRANDS that excel at a number of these different means of differentiation?
Discuss the concept of the internal customer. Who are purchasing's internal customers?
Identify several sources of errors as a student, employee, business owner, or in your personal life. Develop/discuss some Poka-Yokes that might prevent them.
As operations manager. you are concerned about being able to meet sales requirements in the coming months. You have just been given the following production report:
A powder metal (PM) manufacturing line produces bushing in three steps, compaction, sinter-harden, and rough/O?nish turn, which are accomplished at three single machine stations with average processing times of 12, 10 and 6 minutes, respectively.
Recruitment Methodology: List all information every posting must contain and why this information is required to provide a template for hiring managers.
What is a rich media ad? What benefits does it offer the marketer? Does it have any potential downsides? What are the various types of cost? Explain with suitable example. Explain Balanced score card method and its importance in logistic management.
a large scale pharmaceutical manufacturing company estimates based on a shipping fee of 1000 per order that they can
Your response should be a minimum of 200 words in length. You are required to use at least your textbook as source material for your response. All sources used, including the textbook, must be referenced; paraphrased and quoted material must have acc..
The Lucky Loan Company will lend you $10,000 today with terms that require you to pay off the loan in thirty-six monthly installments of $500 each. What is the effective annual rate of interest that the Lucky Loan Company is charging you?
Marketing plan for JPMorgan Chase including: 1) Executive Summary 2) Company Description 3) Strategic Focus and Plan a) Mission Statement (Current) b) New or Revised Mission Statement i) Vision Statement (Current) ii) New or Revised Vision Statement ..
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd