Calculate the expected completion time

Assignment Help Marketing Management
Reference no: EM13737095

Objectives:

Determine the critical path identified by a given PERT/CPM analysis.
Utilize PERT analysis to determine the probability that a given project will meet a specified deadline for completion.
Determine slack time for a given project activity.
Determine scheduled start time for a given project activity.
Determine scheduled completion time for a given project activity.
Use time-cost trade-offs to appropriately crash a project network.

Given: Company A is installing a Web-based customer-feedback system to meet customer needs for quick response when rolling out new products. A new product line is rolling out in 34 weeks and the customer-feedback system must be installed and running in time for the new product launch.

Table shows three estimates of the time it will take Company A to complete each of the activities and project tasks in the customer feedback system project (optimistic, probable, pessimistic). Company B is installing a similar feedback system to accompany a new product line and originally had the same time line as Company A. Company B just announced that its new product line is ahead of schedule and will be launched in 30 weeks instead of the initially projected 34 weeks. Because the Web-based customer feedback system must be installed and running in time for the revised date of the product launch, something must be done to shorten implementation time required for the customer-feedback system project. Refer to Table 1.2 in the attached worksheet "PERT/CPM Tables" that lists the expected time it will take to complete the activities if shortened as much as possible (crash time), the cost to
complete the activity using normal resources (normal cost), and the cost of completing the activity on an accelerated basis (crash cost).

Task:

A. Use the estimates for Company A in Table 1.1 to do each of the following:

1. Determine the expected completion time for each of the ten project activities, entering all your answers in Table 1.1 and showing all your work.

a. Determine the variance for each project activity to two decimal places, entering all your answers in Table 1.1 and showing all of your work.

2. Prepare a PERT chart (network diagram) and identify the critical path for project completion, using your calculated values from part A.

3. Determine each of the following, showing all of your work or reasoning:

a. Expected duration of the entire project
b. Slack for project task A
c. Slack for project task H
d. The week project task F is scheduled to start
e. The week project task I is scheduled to finish

4. Determine the probability of completing this project in time for the product launch in 34 weeks, showing all your work.

B. Assume that Company B has the same expected completion times for project activities as Company A. Use your results from part A1 to calculate the following information, entering all answers in Table 1.2 and showing all of your work:

1. Maximum reduction in time
2. Crash cost per week

C. Identify the following by using your results from part B:

1. Activities to be crashed in order to complete the project within 30 weeks.
2. Number of weeks each of these activities should be crashed to meet the deadline with the lowest possible increase in cost.
3. Additional crashing cost of the activities identified in part C1.

Reference no: EM13737095

Questions Cloud

Compensation plan outline : Evaluate the existing compensation plan to determine if it is the most appropriate for your company. Explain your rationale.
How your topic relate to what we have discussed in class : How does it relate to what we've discussed in class? Why is it important? What can we learn from it today? Why did you choose this document or artifact? What is it?
Analyze master improvement plans and review plans : Analyze master improvement plans and review plans used to achieve long-term improvement efforts.
Calculate the expected completion time : Determine the critical path identified by a given PERT/CPM analysis. Determine the expected completion time for each of the ten project activities, entering all your answers in Table 1.1 and showing all your work
Calculate the expected completion time : Determine the critical path identified by a given PERT/CPM analysis. Determine the expected completion time for each of the ten project activities, entering all your answers in Table 1.1 and showing all your work
What will be your financial break-even point : What will be your financial break-even point. If you require investment capital, identify possible sources (friends, family, banks, USSBA, etc.).
Human resources planning and employee relations : Building on the work that you completed in Assignment continue evaluating the role of functions HR in creating a set of Human Resources' policies and procedures for the acute care hospital.
What is the budgeted accounts receivable balance : What is the budgeted accounts receivable balance from July sales on July 31?
Consultants to support hrm : Suggest a key driver for a health care administrator to engage the services of a consultant to improve the functions of HR.

Reviews

Write a Review

Marketing Management Questions & Answers

  How do you define the direct marketing

How do you define the direct marketing ? or give some examples specific.

  Explain managing organizational change

Explain Managing Organizational Change and first and foremost in Organizational Change Management a successful project is to develop a plan to produce the desired results and remain within budget

  Explain impact of ebusiness

Explain impact of eBusiness and Describe where you think eBusiness is taking us in the future

  Analyze the shifts in organizational structure and

write a three to four 3-4 page paper in which you1. reflect on a time when you or someone elsersquos good intentions

  Explain and analyze amazon

Explain and Analyze Amazon and What information forms the basis of your decision and pay special attention to the company's three-year trends in revenues

  Email marketing is another way to reach your target

traditional advertising mediathis week we will focus mainly on the different forms of advertising media.first we will

  Discuss different direct marketing media

Analyze what direct marketing delivers and the impact on a target market. Discuss different direct marketing media's and the impact across cultures

  Explain key elements of e-business strategy framework

Explain Key Elements of E-Business Strategy Framework with references and specific examples

  What is included in a detailed project plan

Discuss and explain what is included in a detailed project plan and present two reasons why scheduling resources is an important task.

  Formulate and solve a linear programming model

Formulate and solve a linear programming model for Julia that will help you advise her if she should lease the booth

  Explain entrepreneurial perspective

Explain Entrepreneurial Perspective and Formulate and justify three criteria to use when making the choice between narrow-scope and broad-scope market strategies for an established business

  Define and explain what segmentation is and discuss

1.define and explain what segmentation is and discuss different segmentation bases you could use for your

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd