A local nursery greens uses 1560 bags of plant food annually. Green works 52 weeks per year. It costs $10 to place an order for plant food. The annual holding cost rate is $5 per bag. Lead time is one week.

(a) Calculate the economic order quantiy
(b) Calculate the total annual costs
(c) Determine the reorder point

 

Reference no: EM13109551

Questions Cloud

What is the far as well as frr of the biometric system : Presume that an organization has 200 real users. When biometrics are used over a day there are 1000 total access attempts. Only 100 of the access efforts are allowed through though it turns out that only 80 of the 100 allowable through were real u..
Compute the aggregate production rate : The BackPack Company produces a line of backpacks. The manager, Jill Nicholas, has decided that the BackPack Company must have very good customer service.
What is the market for corporate control : What is the market for corporate control? What conditions usually cause this external governance mechanism to become active?
Compute the value of the test statistic t : Compute the value of the test statistic t where the mean for a sample of 12 from the first population is 25.3 with a corresponding standard deviation of 0.31
Calculate the economic order quantiy : A local nursery greens uses 1560 bags of plant food annually. Green works 52 weeks per year. It costs $10 to place an order for plant food. The annual holding cost rate is $5 per bag. Lead time is one week.
Determine the mass in grams of the lead : The water level in a graduated cylinder was at 211 rises initially it raised to 270 after adding a piece of lead is submerged. Determine the mass in grams of the lead?
Five population''s treatments or levels of the factor : five population's treatments or levels of the factor studied are
Compute the final temperature of the mixture : Compute the final temperature of the mixture (assuming no heat loss to the surroundings). The heat capacities of H2O(s) and H2O (l) are 2.08 and 4.18 J/g · °C, respectively, enthalpy of fusion for ice = 6.02 kJ/mol.
Determine the amount of heat energy : Determine the amount of heat energy is needed to raise the temperature of 0.362 kilograms of Cu from 23. Degree Celsius to 60 degree Celsius?

Reviews

Write a Review

Operation Management Questions & Answers

  Explaining the success and failure of companies

It is possible for a company to be the lowest-cost producer in its industry and simultaneously have an output that is the most valued by customers. Which is more important in explaining the success and failure of companies: strategizing or luck?

  Illustrate what is the maximum number of flower pots

Illustrate what is the maximum number of flower pots which are held in inventory in a given ordering cycle. Depend on info below.

  Define what is meant by high-performance organizations

Define what is meant by High-Performance Organizations (HPOs) and describe them in terms of their five key components.

  Explain how many brownies should be forecast

From reviewing historical information, you know which approximately 70percent of the patients will be on diets which allow brownies. Of those, 85percent will likely select the brownies. Approximately explain how many brownies should be forecast.

  Should employers be allowed to monitor employees

Should employers be allowed to monitor employees in the workplace? Should distinctions be made based on whether it is monitoring computers

  The economies are operated through centralized bureaucracies

The economies of countries such as Russia and China have historically been operated through centralized bureaucracies

  Mathematical formulation of the optimization problem

The JLM Ambulance Service serves five rural towns, Abbeville, Benton, Clayton, Dunning and Eden. JLM wants to construct a centralized facility and garage to minimize its total annual travel mileage to those towns

  Constraints and objective function

The problem deals with discussing the differences between constrain and objective function under linear programming.

  Evaluate various supply chain strategy

Evaluate various supply chain strategy considerations for managers moving products or services to the consumer.

  Illustrate what other factors are relevant to this issue

Illustrate what other factors are relevant to this issue. Explain how do the changes in assumptions mentioned by the other managers affect the proposal. Illustrate what position should Jim take.

  A make-to-stock strategy involves holding items in stock

A make-to-stock strategy involves holding items in stock for immediate delivery and is feasible for standardized products with high volumes and reasonably accurate forecasts.

  Estimating breakeven in dollars

GX Corporation is developing a new innovative product. To launch the product, fixed costs are set at $140,000. Variable Costs are set at $75. They desire to break even by selling 1,000 units.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd