A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 70% complete. The planners were only expecting to be 53% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,419,800 and it was done for only $1,299,800. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,499,800 but was actually done for $8,999,800. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,499,800. To date they have spent $4,999,800 on the superstructure.
Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)
Assume that two legal actions follow, one civil and one criminal. Who will be responsible for bringing the civil case? What will be the outcome if the jury believes that Bob did in fact burgle Vince’s house? Who will be responsible for bringing the c..
1. What are the operational challenges associated with developing new boutique hotels?
What are the four basic types of conflict? Describe them. Which type of conflict did you witness or experience?
Illustrate what is objectivity also subjectivity. Elucidate how can a manager minimise subjectivity in her/his decision making. Elucidate how can a manager improve her/his decision making skills.
What are the current strengths in the organization's IM/IT investments?
The owner of Genuine Reproductions (GR), a company that manufactures reproduction furniture, is interested in measuring inventory effectiveness.
A real estate agent is considering changing her cell phone plan. there are 3 plans to choose from, all of which involve a weekly service charge of $20.
he criterion shipment methods take two days. Elucidate but for an additional charge of $500, the container can be sent overnight. The annual holding cost rate for this type of item has been estimated at 28percent. Illustrate what option is more ec..
how could senior management help project leaders to manage effictively in a matrix environment?
Determine the types of inventories these companies currently manage and describe their essential inventory characteristics and analyze how each of their goods and service design concepts are integrated.
Which of the following is a true statement concerning evaluation criteria?
Submit your Synthesis and Final Project Audit by the end of this unit. For the final steps of your audit, be sure to revise your previous assessments based on any instructor feedback. Then synthesize the four assignments you completed from Unit 2 ..
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd