A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 63% complete. The planners were only expecting to be 52% through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,422,000 and it was done for only $1,302,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,502,000 but was actually done for $9,002,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,502,000. To date they have spent $5,002,000 on the superstructure.

Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. (Round your "performance index" values to 3 decimal places.)

 

Reference no: EM13109412

Questions Cloud

Explain approval for the construction of a new nuclear plant : The board of directors of New England Authority has given approval for the construction of a new nuclear power plant. The plant will want an investment of $250 million.
Average income of sold proprietor cpa : A ten year old survey found that the average income of sole proprietor CPA's was $74,914. To update this information, a new survey of 112 proprietor CPA's was taken and it showed a mean of $74,695.
Illustrate what factors account for the considerable amount : Illustrate what factors account for the considerable amount of attention receives from several parties, including activists, business press, writers and academic scholars?
Explain why financial intermediaries relatively effective : Jim fired an employee for creating illustrates what the manager called a poisonous relationship. Example whether or not the employee has a legitimate claim against the industry and the actions the industry should take.
Calculate schedule variance and schedule performance index : A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed.
What happens to consumer as well as producer surplus : What happens to consumer as well as producer surplus when the sale of the good is taxed? How does the change in consumer
Formulate and solve an lp to maximize daisy''s profits : Eli Daisy uses chemicals 1 and 2 to produce two drugs. Formulate and solve an LP to maximize Daisy's profits
Explain the level of account recievable : Standard corporation has annual credit sales of $250 000 as well as an average collection period of 40 days. It plans to change its credit terms from net 40 to 3/10, net 40.This is expected to decrease the average collection period by 10 days.
Identify key gaps in planning for the exit : Identify key gaps in planning for the exit. Provide recommendations on the exit strategy. Is the sale the right one? What steps ought to be taken to maximize the sales-price?

Reviews

Write a Review

Operation Management Questions & Answers

  Determine the total cost of quality

The costs of quality are given by the following equations, Determine the total cost of quality when there are no defectives. D= 0 and product quality is perfect.

  Describe a project selection process

Describe a project selection process from either the literature or an organization of your choice. If it's from the literature, please submit the article; if it's an organization.

  Provide your customers with a tiered service system

If you owned your own business, would you provide your customers with a tiered service system? Why or why not?

  Elucidate what volume of demand would manager have

Elucidate what volume of demand would the manager be indifferent between the 2 cities Which city should be chosen if demand is higher than this volume.

  Describe the moral right to destroy the government by force

When a government is corrupt and it is taking the life of innocent people, do we have the moral right to destroy the government by force? Please explain with specific ethical reasons.

  Explain social responsibility activities and contributions

Social responsibility activities and contributions are mandated legally for large multinational global corporations by the World Bank and the United Nations.

  Lessons from operations management

This solution offers the student with a brief overview of most important thing you could learn from operations management (as well as an example). It's approximately 230 words and one reference is included.

  Define the decision problem

Identify the potential root causes and explain your reasoning; Define the decision problem;

  What strategies are recommended for a firm

Using a Grand Strategy Matrix approach, what strategies are recommended for a firm that is a weak competitor in a slow-growing market? Elaborate on what these strategies could mean for a college or university.

  Human resource challenges

Human Resource Challenges Find at least two articles through ProQuest which discuss at least two of the biggest challenges facing human resource departments today

  What managers do to maximize chances for success

What can top managers do to maximize chances for success here? Cisco went live with ERP in a big bang fashion, which is inherently risky. How did Cisco mitigate this risk?

  A motor grader requires two passes at 2 miles per hour

A motor grader requires two passes at 2 miles per hour, two passes at 3 miles per hour, and one pass at 4 miles per hour to accomplish the work

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd